Scheduling RECD Work Around a Factory’s Annual Shutdown

Most factories in India have one window each year when the production lines stop, the boilers go cold and the maintenance team gets the plant to itself. For many plants that window falls around Diwali, the financial year end or the monsoon slowdown. It is also the window that looks most natural for fitting a Retrofit Emission Control Device (RECD) to the diesel generator (DG) sets, because the generators are not needed to back up production while the lines are down.

That logic is sound, but the shutdown is not a free slot. Every other department wants the same cranes, the same contractors, the same safety officer and the same ten days. If the RECD work is planned late, it ends up squeezed into the last two days, commissioned in a hurry and handed over with a long punch list. If it is planned well, the factory restarts with compliant DG sets, tested under load, with the paperwork ready for the next pollution control board inspection.

This guide is organised as a countdown. “T” is the first day of the shutdown. Each stage says what should be finished by that point and why. Adjust the dates to suit your plant.

Why the Annual Shutdown Is Attractive for RECD Work

Before building a schedule, it helps to be clear about what the shutdown actually gives you, because those advantages are what you are protecting.

The DG sets can be isolated. During normal production, at least one DG set usually has to stay available for grid outages. Taking it out of service for several days means accepting risk, or bringing in a rental set. During a shutdown the essential load is far smaller, so one set can often be locked out while the others cover what remains. Our guide on preserving backup power during an RECD retrofit explains how to think about that residual load.

Lifting equipment is already on site. Many shutdowns bring in a mobile crane or hydra for heavy maintenance. If the RECD needs to go onto a rooftop, a high plinth or over a canopy, sharing that crane booking is cheaper and safer than arranging a separate lift later.

Permits and supervision are concentrated. The safety team runs a permit-to-work system at full strength during the shutdown, with dedicated permit issuers, fire watchers and gas testers. Hot work, work at height and electrical isolation are all easier to arrange when that system is already staffed.

There is time to test. Without production pressure, the DG sets can be run on a load bank or on available plant load, and the RECD can be commissioned properly rather than switched on and left.

Why the Shutdown Is Also Risky

Contractors are scarce. Fabricators, riggers and electricians are booked by every factory in the industrial belt at the same time of year. A contractor who is free in August may have no crew left in late October.

Cranes and permits are shared. The crane may be committed to the boiler or a press line on exactly the day the RECD arrives. Hot work permits may be limited because the same area has other jobs running.

The DG may be needed during the shutdown. Shutdown work often needs temporary power: welding sets, lighting, pumps for tank cleaning, test rigs. If the grid supply to a bay is isolated for HT panel maintenance, the DG sets may be the only source of power for other contractors. A DG that is half-dismantled for RECD fitment cannot supply that.

Lead times are fixed. The shutdown date does not move because a device was dispatched late. An RECD is sized to the specific engine’s displacement, exhaust flow and duty (see why same-kVA sets can need different RECDs), so a unit cannot always be pulled from stock at short notice. Fabricated adaptors, supports and flanges add their own lead time.

The Countdown: T-6 Months to T+4 Weeks

T-6 months: decide scope and confirm the window

  • Confirm the shutdown dates with the plant head and production planning. Get the planned start, the planned restart and any known “no-go” days (for example, an HT supply outage on day 3).
  • List the DG sets in scope. Note make, model, kVA, engine model, year, running hours and current exhaust layout. Nameplate and exhaust photos help the supplier.
  • Check the compliance driver. Is this fitment needed for a consent condition, a GRAP-related restriction in Delhi NCR or a state board direction? The driver affects how much slack you have if something slips. The DG set emission regulations page and the CPCB website are the starting points; your consent to operate is the document that actually binds you.
  • Decide whether all sets go in this shutdown. With two or three sets, doing all of them may be realistic. With more, a phased plan may be safer.
  • Name an owner. One person, usually from maintenance or EHS, should own the RECD package within the shutdown plan.

T-5 months: site survey and trial fit check

  • Measure the exhaust path from turbo outlet or manifold to the existing silencer and outlet. Record pipe diameters, flange standards, bends, supports and wall penetrations.
  • Check space and access. Can the device be brought into the DG room through existing openings? Is there clearance for maintenance access to the filter later?
  • Record back-pressure if a reading is possible, along with the engine maker’s allowable limit. An RECD adds restriction, and the design must stay within the engine’s limit (see how exhaust back-pressure affects a DG set).
  • Identify power and cable routes for the RECD controller, sensors and any heater.
  • Do a trial fit check using dimensioned drawings or a simple template. Some teams mock up the device envelope with a plywood or cardboard box at the proposed location. It quickly shows whether a door swing, cable tray or duct is in the way.

T-4 months: specification, order and drawings

  • Issue the technical specification or RFQ, including the shutdown dates as a hard delivery constraint.
  • Place the order for the RECD and confirm the dispatch date in writing, with a margin of at least three to four weeks before T.
  • Ask for a general arrangement drawing showing the device position, supports, flanges and connection points.
  • Agree who does what. Supply-only and turnkey orders split responsibilities very differently. Write it down early.

Ordering by lead time

Not everything has the same lead time, and the longest item sets the schedule. A simple way to manage this is to list every item and order them in descending lead time. The figures below are illustrative; your suppliers will give their own.

ItemIllustrative lead timeOrder byNotes
RECD unit (sized per engine)8–12 weeksT-4 monthsConfirm sizing data before order
Custom adaptor spools and flanges4–6 weeksT-3 monthsNeeds final GA drawing
Support steel (frame, brackets)3–4 weeksT-3 monthsStructural check if wall or roof mounted
Flexible bellows / expansion joints3–6 weeksT-3 monthsSize from survey data
Controller, sensors, cables2–4 weeksWith RECD orderOften supplied with the device
Insulation and cladding2–3 weeksT-2 monthsConfirm temperature class
Crane / hydra bookingVariesT-3 monthsBook jointly with shutdown plan
Load bank hire (if used)2–4 weeksT-2 monthsSize in kW to match test points

The sequence matters more than the numbers. If the adaptor spools cannot be fabricated until the GA drawing is approved, and the GA drawing waits for survey data, then a late survey pushes everything. Work backwards from T and the survey usually needs to happen earlier than expected.

T-3 months: pre-fabrication plan

The shutdown window should be used for work that can only be done when the DG is isolated. Everything else should be done before.

Work that can usually be pre-fabricated or pre-installed:

  • Support frames and brackets, fabricated off site to the GA drawing and painted.
  • Adaptor spools with flanges welded and pressure-tested off site, so only bolting is left for the shutdown.
  • Cable trays and conduits for controller and sensor cables, if the route does not pass near hot surfaces that are live during production.
  • Controller mounting and power supply, if a suitable panel position exists away from the DG.
  • Foundation or plinth work, where curing time would otherwise eat into the shutdown.

The more of this list you clear, the shorter the actual DG outage becomes.

T-2 months: permit-to-work and coordination with other shutdown jobs

At this stage the RECD package must be inside the master shutdown plan, not running alongside it.

  • Submit the RECD job list to the shutdown planner with durations, crew sizes, crane needs and permit types.
  • Map permit types. RECD fitment typically needs electrical isolation (lockout-tagout of the DG and its starting system), hot work (cutting and welding of the exhaust), work at height (high-level exhaust, roof outlets) and lifting permits.
  • Check clashes. Are other contractors working in the DG room, on the HT panel or on the roof at the same time? Is the fire watch shared?
  • Confirm temporary power needs. Ask every shutdown contractor what power they need and from where. If any of it depends on the DG sets, decide which set stays available and on which days.
  • Agree the test plan with the DG maintainer, including the load source for commissioning.

T-1 month: material readiness and site preparation

  • Track the RECD dispatch and inspect on arrival using a delivery inspection checklist. Damage found at T-2 days cannot be fixed in time; damage found at T-3 weeks often can.
  • Stage materials near the DG area: supports, spools, gaskets, fasteners, insulation, cable.
  • Pre-install what you can: cable trays, controller panel, support frames that do not need the DG off.
  • Brief the crew on the day-by-day plan and the permit sequence.
  • Hold a go/no-go review at T-7 days. If a critical item is missing, decide now whether to proceed, phase or fall back (see the contingency section).

The Shutdown Window: Day-by-Day Plan

The shutdown itself should feel boring, because every task has been rehearsed on paper. A typical sequence for one DG set looks like this:

  1. Isolate and lock out the DG: breaker, starting batteries, fuel valve if relevant. Confirm the engine is cool enough for exhaust work.
  2. Remove existing exhaust sections that will be replaced or relocated. Tag and keep them until commissioning is complete, in case you need to restore the original layout.
  3. Install supports that could not be pre-installed.
  4. Lift and position the RECD, then fit adaptor spools, bellows and gaskets. Follow the step-by-step installation process, and never leave unsupported weight on the turbo outlet.
  5. Fit sensors and run cables, keeping them clear of hot surfaces.
  6. Insulate and clad where the design calls for it.
  7. Pre-commissioning checks: bolt torques, gasket seating, support alignment, sensor wiring, controller power.
  8. Remove isolation under the permit system and hand the set over for testing.

The time sinks are usually the lift (waiting for a crane), hot work (waiting for a permit or a fire watcher) and fit-up problems with adaptors. That is why pre-fabrication and early permit planning matter more than crew size.

Commissioning and Load Testing Before Restart

Do not leave commissioning until the day before restart. Once production restarts, the DG sets go back to standby duty and running them on load for testing becomes much harder.

A sensible commissioning sequence:

  • First start and leak check at no load. Look and listen for exhaust leaks at every joint.
  • Warm-up before taking any readings. The RECD needs hot exhaust to stabilise (see warm-up time for RECD testing).
  • Load steps, for example 25%, 50% and 75% of rated kW, holding each long enough for temperatures to settle. A resistive load bank runs at unity power factor, so set test points in kW rather than kVA.
  • Back-pressure reading at the highest practical load, compared with the engine maker’s limit.
  • Controller and alarm checks: sensor readings, alarm thresholds, any link to the BMS or DG controller.
  • Emission or opacity testing where required by the consent or the order.
  • Operator handover, including a short training session.

If the factory does not hire a load bank, plant load during the shutdown is often too low and too erratic for good test data. That is a strong argument for booking a load bank at T-2 months. The DieselNet technical reference is a good source if your team wants background on how diesel particulate filters behave under different exhaust temperatures and regeneration conditions.

The Punch List

Close as many small open items as possible before restart, because access gets harder once the plant is running. Typical RECD punch items are missing insulation on a short pipe section, untagged cables, paint touch-up on supports, a final torque check after the first hot run, warning labels near hot surfaces, as-built drawing updates and test reports still to be issued.

Classify each item as “must close before restart”, “close within two weeks” or “close at first service”. Our guide on closing the RECD punch list before handover has a fuller method.

Contingency: What If the RECD Is Late?

Despite good planning, a device or a fabricated part can still arrive late. Decide your fallback before T-7 days, not on day 4 of the shutdown.

Situation at go/no-go reviewFallback optionWhat you still gain
RECD delayed by days, within shutdownMove RECD work to the end of the window; keep supports and cabling earlyPre-work done; tight commissioning
RECD delayed beyond shutdown, supports readyInstall supports, spools, cables and controller; fit RECD later in a short planned outageLater outage cut to 1–2 days
One of two units delayedFit the available unit; schedule the second set as a single-set outageOne set compliant at restart
Adaptor spools wrong or missingRefit the original exhaust; re-fabricateSet returns to service safely
Commissioning incomplete at restartRun set only for essential standby; complete testing in first weekAvoids rushed, unrecorded testing

Whatever the option, keep the original exhaust parts until the new layout is accepted. If compliance deadlines are tight, tell the EHS lead who handles consent correspondence early.

Post-Restart: T+1 to T+4 Weeks

  • T+1 week: re-torque flanges and support bolts after several heat cycles. Check sensor readings against commissioning values. Close “must close” punch items if any slipped.
  • T+2 weeks: review controller logs and alarms. Look for patterns such as rising back-pressure or nuisance alarms. Confirm operators are recording what they should.
  • T+3 weeks: issue final as-built drawings, test reports and the O&M manual into the maintenance system.
  • T+4 weeks: hold a short lessons-learned review. What took longer than planned? What should be ordered earlier next time? Add the RECD checks to the monthly DG checklist.

Worked Example: A 10-Day Shutdown with Two DG Sets (Illustrative)

The numbers below are illustrative and not from a specific site.

The plant: an auto component factory in the NCR with two DG sets, DG-1 (500 kVA) and DG-2 (380 kVA), both in a ground-floor DG room with exhaust running up an external wall to roof level. The annual shutdown runs for 10 days. Grid supply is available through the shutdown except on Day 2, when the HT panel is isolated for maintenance from 08:00 to 18:00.

The constraints:

  • On Day 2, one DG set must supply temporary power (about 120 kW) for lighting, welding and the dewatering pumps.
  • The crane is booked for the press line on Days 4 and 5, but free on Days 3 and 6.
  • Hot work permits in the DG room are limited to one crew at a time.
  • A load bank of 400 kW is hired for Days 8 and 9.

The decision: fit DG-2 first, because DG-1 is larger and better suited to cover the Day 2 temporary load. DG-1 is isolated only from Day 3.

Pre-work completed before T: support frames for both sets fabricated and painted; adaptor spools fabricated and leak-tested; cable trays and controller panels installed; both RECDs delivered and inspected at T-3 weeks.

TaskD1D2D3D4D5D6D7D8D9D10
Permits, LOTO DG-2â– 
DG-2 exhaust removal, supportsâ– â– 
DG-1 supplies temp power (HT outage)â– 
DG-2 RECD lift (crane)â– 
DG-2 spools, bellows, sensorsâ– â– 
Permits, LOTO DG-1â– 
DG-1 exhaust removal, supportsâ– â– â– 
DG-2 insulation, pre-commissioningâ– 
DG-1 RECD lift (crane)â– 
DG-1 spools, bellows, sensorsâ– â– 
DG-2 first start, leak checkâ– 
DG-1 insulation, pre-commissioningâ– 
DG-2 load bank testâ– 
DG-1 load bank testâ– 
Punch items, handover, trainingâ– â– 
Buffer dayâ– 

What the plan does well:

  • DG-1 stays available on Day 2 for temporary power, and DG-2 becomes available again from Day 6 as a backup for the rest of the shutdown.
  • Both lifts use the crane on its free days (3 and 6).
  • Hot work in the DG room never has two crews at once: DG-2 hot work ends on Day 4, while DG-1 work on Days 3 to 5 is mostly removal and support fitting, with cutting sequenced around DG-2.
  • Each set gets a full load bank day, with time for warm-up and stepped load points (for example 100, 200 and 300 kW on DG-2 with its 304 kW rating, and 100, 200, 300 and 360 kW on DG-1 with its 400 kW rating).
  • Day 10 is mostly buffer. If anything slips by a day, restart is still protected.

Frequently Asked Questions

How long does RECD fitment usually take on one DG set?

It depends heavily on the exhaust layout and how much is pre-fabricated. With supports and spools ready, mechanical fitment on a straightforward ground-level set can often be done in two to three working days, plus a day for commissioning. Rooftop outlets, long exhaust runs or difficult access add time. The RECD installation timeline guide gives a broader view.

Can we fit the RECD during the shutdown and commission it later?

You can, but it is not ideal. Once production restarts, the DG sets return to standby and getting a few hours of controlled load becomes harder. If commissioning must slip, plan a specific date in the first week after restart and keep the set restricted to essential duty until testing is complete.

What if our DG sets are needed for power during the shutdown?

Ask every shutdown contractor about their power needs at T-2 months. Then sequence the RECD work so at least one set is available on the days when grid supply is isolated. The worked example above shows one way to do this with two sets. With a single set, a short rental may be the safer option.

What paperwork should we have at restart?

At minimum: the test report with load points and back-pressure readings, the as-built GA drawing, the device’s CPCB certification or test documents, sensor details and the operator handover record. Keep them where an inspector can see them quickly.

Related Reading

Plan Your Shutdown Fitment with Aceget

A good shutdown plan starts with the right device, the right data and enough lead time. Aceget supplies CPCB type-approved Retrofit Emission Control Devices for DG sets from 25 kVA to 2500 kVA. You can review our certifications, and if your annual shutdown is coming up, contact our team early with your DG details and shutdown dates so the order and delivery can be planned around your window.