Managing RECD Projects in Buildings with Several Equipment Owners

Fitting a Retrofit Emission Control Device to one generator owned by one company is a fairly contained job. The owner decides, pays, signs the purchase order and keeps the records. Things get far more complicated in a building where the generators belong to different people. A Gurugram office tower may have landlord-owned sets serving common areas, a bank on the ground floor with its own 250 kVA set, and a food court operator with another. A residential complex may have sets owned by the RWA but operated by a facility management company that reports to a builder who has not fully handed over. Each party has a different budget cycle, a different appetite for risk and a different idea of who should pay.

The technical work in these buildings is no harder than anywhere else. What fails is coordination. Roof access is refused because a lease does not mention it, a shared chimney cannot be modified until three parties agree, or one tenant’s set is left out and the whole building looks non-compliant during an inspection. This guide is built around two tools that prevent those failures: a stakeholder map, which tells you who is involved and what they control, and a governance model, which tells you how decisions get made, paid for and recorded. An illustrative worked example with a cost-allocation table follows at the end.

Part 1: The Stakeholder Map

Before anyone discusses an RECD model, draw the map. A stakeholder map is a list of every party that owns, operates, approves, pays for or is affected by a generator, with a note on what each one controls. It sounds like paperwork, but it is the most useful document in these projects because it shows the gaps before they become disputes.

Common ownership patterns

Most Indian buildings with several equipment owners fall into one or more of these patterns.

PatternWho owns the DG setsWho operates themTypical friction point
Landlord-owned, tenant-servedBuilding owner or landlordFM company for the landlordTenants resist cost pass-through in maintenance charges
Tenant-owned sets in a landlord buildingIndividual tenants (bank, data room, restaurant)Tenant’s AMC vendor or the FM companyRoof, shaft and chimney rights sit with the landlord
FM-operated mixed fleetLandlord and tenantsOne FM company runs all setsFM has operational control but no spending authority
Society or RWA-ownedResidents’ welfare association or societyFM agency or in-house staffCommittee approvals and general body timing
Anchor tenantAnchor (hypermarket, cinema, hospital wing)Anchor’s own engineering teamAnchor may set its own technical standards

The pattern decides where authority sits. In a landlord-owned building, the landlord can usually drive the project and recover costs later. Where tenants own sets, the landlord controls the space but not the equipment, and each tenant controls its equipment but not the space. Neither can finish the project alone. For malls, see our guide on RECDs for shopping malls coordinating DG retrofits across tenants.

What each stakeholder controls

For each party on the map, record what equipment they own, what space they control, what they can approve and what they can spend.

StakeholderOwnsControls spaceCan approveCan spend
LandlordCommon sets, chimney, structureRoof, shafts, DG yard, basementStructural, roof and shared exhaust changesOwn sets; shared works if the lease allows
TenantOwn DG setLeased premisesChanges to own setOwn RECD and installation
FM companyUsually nothingDay-to-day accessWork permits, shutdown windowsUsually none without client approval
RWA / societyCommon sets and areasCommon areasVia committee or general bodySinking fund or levy, per bye-laws
Consent holderVariesVariesSPCB applications and responsesVaries

The last row is the one people forget. The consent to operate, or the DG registration, is held by a specific legal entity. That entity, not the FM company and not the RECD supplier, is typically the one the State Pollution Control Board looks to during an inspection. Find out who it is for every set before planning starts. In some buildings the landlord holds one consent listing all sets; in others each tenant registered its own set.

Physical rights: access, shafts and roofs

RECDs take space, add weight and need cable runs for controllers and sensors. In a multi-owner building each of those may need a right that belongs to someone else.

  • Roof rights. A roof-mounted RECD needs the landlord or society to permit the location, the structural load and the crane or hoist. See rooftop RECD installation, structural support, lifting and access.
  • Shaft rights. Exhaust pipes often rise through a shared shaft. Adding an RECD or a support bracket touches space the tenant does not lease.
  • Basement DG rooms. A tenant set may sit in a demised bay, but the corridor, ventilation and lifting route are common areas.
  • Cable routes. Controller power and BMS signal cables may cross other tenants’ premises or common trays.
  • Working hours. Hot work, crane lifts and noisy fabrication need a work permit, usually from the FM company.

Check leases early. Many older leases say nothing about modifying exhaust systems, which leaves the decision to negotiation. Put the agreed rights in a short access letter or lease side letter before any purchase order is placed.

Shared exhausts and chimneys

The hardest physical issue is a shared chimney. Some buildings connect several sets into one stack to meet chimney height rules. An RECD is normally fitted on each engine’s own exhaust line before it joins the shared section, because each device is sized to one engine’s displacement, exhaust flow and duty. One large device on a common header raises questions about back-pressure interaction between engines, so treat that as a specialist decision. Our post on whether two diesel generators can share one RECD explains why.

Even with one RECD per set, the shared section matters. Each device adds back-pressure to its line, and the combined effect on a shared stack has to be reviewed, especially when sets run together. Measure back-pressure on every line with the other sets running as they would in an outage. The basics are in how exhaust backpressure affects a DG set, and DieselNet is a useful technical reference on diesel exhaust aftertreatment. The owner of the stack, usually the landlord, should hold the drawings and approve every change.

Part 2: The Governance Model

With the map done, design the governance. A governance model answers five questions: who leads, who decides, who pays, who talks to whom, and what happens when people disagree. A two-page project charter signed by every owner is better than a fifty-page agreement nobody reads.

Layer 1: A project lead and a single point of contact

Someone has to drive the project. The natural lead is usually the party that controls the shared space: the landlord or the society. The lead does not need to own every set. Its job is to run the timetable, chair meetings, hold master documents and coordinate suppliers.

Separately, appoint a single point of contact (SPOC), one named person, often a senior FM engineer, who handles day-to-day questions from suppliers, installers and tenants. Suppliers should not get different instructions from four owners. Every technical query goes through the SPOC, who answers it or routes it to the right owner and records the answer. Write down the SPOC’s deputy, what they can decide alone (permit timing, access, minor routing), what they must escalate (cost, scope, anything touching another owner’s equipment) and how quickly owners must respond, for example within three working days.

Layer 2: Decision rights

Not every decision needs every owner.

Decision typeExamplesWho decides
IndividualRECD model for a tenant’s set, that tenant’s payment termsOwner of that set
Shared technicalChimney changes, common supports, roof location, back-pressure limits on a shared stackLandlord or society, after consulting affected owners
Shared commercialCost-allocation method, common contractor, testing scheduleAll owners, under an agreed consent rule

“Unanimous” sounds fair but gives any one owner a veto. A common alternative is that the lead proposes, owners have a fixed period to object with reasons, and unresolved objections go to the escalation ladder. In societies, check the bye-laws, because some spending needs a general body resolution.

Layer 3: Who pays for what

Split costs into two buckets.

Set-specific costs belong to that set’s owner: the RECD, controller, set-specific supports, installation on that exhaust line and that set’s testing. For budgeting, see RECD cost in India.

Shared costs benefit more than one owner: structural assessment of the roof or DG yard, shared chimney modifications, crane hire or scaffolding used for several sets, common cable trays and BMS gateways, project coordination, and testing mobilisation booked once for the building.

Shared costs need an allocation method. There are three common bases.

MethodHow it worksStrengthWeakness
By installed kVAProportional to rated capacitySimple, uses undisputed nameplate dataIgnores how much each set runs
By run hoursProportional to recorded hours over a reference periodReflects actual useRecords may be incomplete; one bad outage year skews it
By share of load (kWh)Proportional to energy generatedClosest to each set’s emission footprintNeeds a reliable energy meter on each set

A hybrid is often fairest: size-driven works by kVA, use-driven costs by run hours. Use data every owner can check, such as nameplates, hour meters and DG load logs, and fix the reference period in writing so nobody can cherry-pick one later. Also check the lease. Many allow a landlord to recover compliance works through common area maintenance charges; others forbid it. The charter should not contradict the lease without an agreed variation.

Layer 4: Consent holder and compliance records

Every set needs a named consent holder, and the project should keep compliance records in one place even though the equipment has several owners. An inspector usually sees one site, not four businesses. If the landlord’s sets are fully documented and a tenant’s set has nothing, the building as a whole may face questions. Our guide on what happens during a pollution control board inspection explains what is checked.

Keep a shared compliance folder with, for each set: owner, consent holder and reference number; RECD make, model and type-approval certificate (see how to verify a CPCB-tested RECD); commissioning report and test results; maintenance and cleaning records; and the supplier and AMC contacts. Each owner keeps its originals, but copies sit in the shared folder so the SPOC can produce them. For the regulatory background, see the CPCB website and our page on DG set emission regulations.

Layer 5: The communication plan

Multi-owner projects fail quietly when people stop hearing about progress.

AudienceWhat they needChannel and frequency
All ownersProgress, cost status, decisions dueWritten update fortnightly, meeting monthly
Tenant operations staffShutdown windows, access limitsEmail and notice board, 7 days ahead
FM and securityPermits, crane movements, hot workPermit system, daily briefing during works
Suppliers and installersTechnical answers, site rulesThrough the SPOC only, logged
Occupants or residentsNoise, lift use, parking blocksCircular or notice before each disruptive activity

Shutdown windows need special care. A tenant with a data room or clinic may not accept its set being out of service in working hours, and may also rely on the landlord’s sets as a second layer of backup. Sequence the work so no owner loses all backup at once; our guide on preserving backup power during an RECD retrofit shows how. In Delhi NCR, plan around GRAP too, because a building with some sets fitted and others not faces awkward choices in winter. See GRAP stage 1 to 4: what changes at each level.

Layer 6: Dispute avoidance

Most disputes are about money, access or blame. You can make them smaller.

  1. Agree the allocation method before quotes arrive. Once owners see numbers, each prefers the method that suits it.
  2. Use one technical reference: one drawing set, one back-pressure limit per set, one testing protocol.
  3. Record every scope change with a note on who pays. See managing scope changes after an RECD order.
  4. Separate snagging by owner, so one party’s open item does not hold up another’s handover.
  5. Set an escalation ladder with time limits: SPOC, then owners’ representatives, then senior management, then an independent technical expert for technical issues.
  6. Keep numbered minutes, circulated within two days. Disputes often start with “we never agreed that”.

Worked Example: A Mixed-Use Building in Noida (Illustrative)

The figures below are illustrative only. They show the method, not real prices or a real building.

The building

A ten-storey mixed-use building has retail below and offices above.

SetOwnerRatingLocationServes
DG-1Landlord750 kVARoofCommon areas, lifts, shared tenant backup
DG-2Landlord750 kVARoofCommon areas, lifts, shared tenant backup
DG-3Tenant A (bank branch and data room)250 kVABasement bayTenant A only
DG-4Tenant B (anchor restaurant group)500 kVARear yardTenant B only

Total installed capacity is 750 + 750 + 250 + 500 = 2,250 kVA. DG-1 and DG-2 share a roof chimney. DG-3 exhausts through a shaft rising past other tenants’ floors. DG-4 has its own short stack. The FM company operates DG-1 and DG-2, issues permits for the building and acts as SPOC. The landlord holds the consent for its two sets; each tenant holds its own registration.

The shared cost pool

Each owner buys and installs its own RECD. The shared pool is:

Shared itemIllustrative cost (₹)
Structural assessment of roof and shaft supports1,50,000
Chimney and shaft modifications, support brackets6,00,000
Crane hire and roof access works (one mobilisation)2,50,000
Project coordination and SPOC time1,20,000
Coordinated testing mobilisation80,000
Total12,00,000

Check: 1,50,000 + 6,00,000 + 2,50,000 + 1,20,000 + 80,000 = 12,00,000.

Reference data (last 12 months, illustrative)

OwnerInstalled kVARun hoursEnergy generated (kWh)
Landlord (DG-1 + DG-2)1,5004002,02,500
Tenant A (DG-3)25015022,500
Tenant B (DG-4)50025075,000
Total2,2508003,00,000

Landlord hours are the two sets combined. A sense check on the energy column: Tenant A’s 22,500 kWh over 150 hours averages 150 kW, about 75% of a 250 kVA set’s 200 kW at 0.8 power factor. Tenant B’s 75,000 kWh over 250 hours is 300 kW, also 75% of 400 kW. The landlord’s 2,02,500 kWh over 400 set-hours is about 506 kW per running hour.

Allocation under each method

OwnerkVA shareBy kVA (₹)Hours shareBy hours (₹)kWh shareBy kWh (₹)
Landlord66.67%8,00,00050.00%6,00,00067.50%8,10,000
Tenant A11.11%1,33,33318.75%2,25,0007.50%90,000
Tenant B22.22%2,66,66731.25%3,75,00025.00%3,00,000
Total100%12,00,000100%12,00,000100%12,00,000

The working:

  • kVA: 1,500 ÷ 2,250 = 2/3, so ₹8,00,000. 250 ÷ 2,250 = 1/9, so ₹1,33,333. 500 ÷ 2,250 = 2/9, so ₹2,66,667.
  • Run hours: 400 ÷ 800 = 50%, so ₹6,00,000. 150 ÷ 800 = 18.75%, so ₹2,25,000. 250 ÷ 800 = 31.25%, so ₹3,75,000.
  • kWh: 2,02,500 ÷ 3,00,000 = 67.5%, so ₹8,10,000. 22,500 ÷ 3,00,000 = 7.5%, so ₹90,000. 75,000 ÷ 3,00,000 = 25%, so ₹3,00,000.

Each column totals ₹12,00,000.

What the numbers show

Tenant A’s bill ranges from ₹90,000 to ₹2,25,000, a factor of 2.5. Its set is small but runs a relatively high number of hours for its size, so run hours penalise it, while its modest energy output means kWh favours it. The landlord pays least under run hours because its two large sets run relatively few hours for their combined capacity. This is exactly why the method must be agreed before anyone sees the figures.

The agreed hybrid

The owners agree that size-driven works should follow kVA and use-driven costs should follow run hours. To keep it simple, they split the whole pool 50% by kVA and 50% by run hours.

OwnerHalf of kVA allocation (₹)Half of hours allocation (₹)Hybrid total (₹)
Landlord4,00,0003,00,0007,00,000
Tenant A66,6671,12,5001,79,167
Tenant B1,33,3331,87,5003,20,833
Total6,00,0006,00,00012,00,000

Check: 7,00,000 + 1,79,167 + 3,20,833 = 12,00,000.

Tenant A then points out that part of the shaft work serves only DG-3. That is a fair challenge. If ₹1,00,000 of the chimney and shaft line relates only to DG-3, it should move to Tenant A as a set-specific cost and the shared pool should drop to ₹11,00,000 before allocation. Splitting line items honestly does more for trust than any formula.

How it ran

The landlord led, and the FM chief engineer was SPOC. All owners signed a two-page charter covering the cost method, decision rights, escalation ladder and shared compliance folder. DG-1 and DG-2 were fitted one at a time so landlord backup was never fully lost. DG-3 was fitted on a Sunday with the landlord’s sets confirmed available. One crane booking served both roof devices and DG-4’s yard device, which is why crane hire sat in the shared pool. Back-pressure was recorded on every line, with the other sets running, against one agreed limit per set.

Frequently Asked Questions

If the landlord fits RECDs but a tenant refuses, who is responsible?

Typically, each consent or registration holder is responsible for its own set. A landlord cannot usually force a tenant to buy equipment unless the lease allows it, though it may rely on lease clauses requiring tenants to follow applicable law, or control access for works on its roof and shafts. Check the lease and take legal advice if the tenant will not move.

Can one supplier handle every set in the building?

Yes, and it often simplifies coordination, testing and spares. Each owner must still agree to it, and each RECD must be sized to its own engine. One supplier does not mean one model. See choosing CPCB-approved RECD vendors.

What if run-hour records are missing for one set?

Agree a fallback in the charter: use kVA for that set, or an estimate all owners accept. Do not let one missing record block the whole allocation.

Does the FM company carry compliance responsibility?

The FM company is responsible for what its contract says, such as daily checks and records. Legal responsibility under the consent typically stays with the consent holder. Our companion post on who owns RECD performance when generator operation is outsourced explains the split.

What if a set changes owner mid-project?

Treat it as a scope change. Update the map, transfer documents, confirm the new owner accepts the agreed allocation, and check whether the consent or registration needs updating.

Talk to Aceget About Your Building

Aceget supplies CPCB type-approved Retrofit Emission Control Devices for DG sets from 25 kVA to 2500 kVA. If your building has several equipment owners, our team can review each set’s details so devices are sized individually while the project runs on one plan. Review our certifications or contact our team to discuss your site.