How to Preserve Backup Power During an RECD Retrofit

Most sites buy an RECD for their DG set to keep running it legally. The irony is that installing one usually means the DG cannot run for a while. For a single-set building, that is a window in which a grid failure leaves the lifts, the server room, the fire pumps or the ICU with nothing behind them.

That window can be managed. With planning, a site can keep backup power available for almost the whole project, and reduce the true “no backup” period to a few hours that are chosen carefully, announced in advance and covered by a contingency plan.

This guide is organised as a timeline, from the first planning meeting to the day the DG is formally handed back. An illustrative worked example for a 500 kVA single-set hospital annexe follows at the end.

The Core Risk: A Site with No Generator

During an RECD retrofit, the DG is typically unavailable for some combination of:

  • Exhaust work: removing a section of the existing exhaust, fitting the RECD and its connecting pieces, and re-supporting the line.
  • Controller and sensor work: mounting the controller, running cables, connecting sensors and, where applicable, the heater supply.
  • Testing: back-pressure checks at load, controller checks and any emissions or performance tests agreed in the contract.

On a site with two or more sets, the others can carry the load (see the sibling post on sequencing RECD installations on an N+1 generator system). On a single-set site, the building is exposed for every hour the DG is out of service.

The RECD installation timeline guide gives typical durations. The aim here is to shorten the backup gap further, or close it with a temporary set.

Timeline at a Glance

PhaseWhen (relative to work start, “Day 0”)Key outputs
1. Planning8 to 4 weeks beforeLoad list, backup strategy decision, rental DG sizing, approvals started
2. Choosing the window6 to 3 weeks beforeAgreed dates, outage-season and GRAP check, critical-load sign-off
3. Pre-work3 weeks to 1 day beforePre-fabricated parts, trial fit, cable routes ready, rental set connected and tested
4. The outage windowDay 0 to Day NDG isolated, RECD fitted, made-safe points each evening
5. Return to serviceDay N to Day N+2Checklist complete, load test, DG back in auto, rental released
6. Close-outUp to 2 weeks afterPunch list closed, documents filed, lessons recorded

Durations are typical ranges. Difficult rooftop or basement access stretches Phases 3 and 4.

Phase 1: Planning (8 to 4 Weeks Before)

Step 1: Map what the DG actually protects

Start with a list, not an assumption. Walk the DG’s outgoing feeders and write down every load it backs up, then mark each as one of:

  • Life safety: fire pumps, emergency lighting, smoke extraction, lifts used for evacuation, medical gas alarms.
  • Business critical: server rooms, cold storage, pharmacy refrigeration, process equipment that cannot be interrupted.
  • Comfort or convenience: general lighting, HVAC for offices, non-essential lifts.

Then note which already have their own backup. A server room on a UPS with 20 minutes of battery survives a blip, not a four-hour grid failure.

Step 2: Use real load data

Pull the DG’s load logs for the last few months, especially for any long outages, and find the actual peak and typical running kW. The guide on using DG load logs to assess RECD suitability explains how to read them. If logs do not exist, take clamp-meter readings during a planned test run with the critical loads switched on.

Do not size the temporary arrangement from the nameplate. A 500 kVA DG that has never seen more than 260 kW does not need a 500 kVA hire set.

Step 3: Decide the backup strategy

There are four realistic options. The right one depends on the critical load, the grid record and the budget.

OptionWhat it meansSuitsMain risk
A. Full rental coverHire set sized for all DG loads, connected for the whole outage windowHospitals, data rooms, sites with frequent long outagesCost; connection work
B. Critical-load rentalSmaller hire set feeding only life-safety and critical loadsOffices, hotels, malls with clear load separationNeeds a suitable panel or changeover point
C. Short-window, no rentalWork squeezed into a few hours at a low-risk time, with the DG kept restorableSites with reliable grid and UPS-backed critical loadsGrid failure during the gap
D. Accept riskNo special measuresOnly where no life-safety or critical load depends on the DGUsually not acceptable for occupied buildings

Where people’s safety depends on the DG, choose Option C only if the “no backup” hours are short, the grid is historically stable then, and the DG can be restored quickly. Hospitals should normally plan for Option A or B; the post on RECDs for hospitals and critical backup loads covers the clinical side in more detail.

Step 4: Size the temporary DG

If you are hiring, size it from the load you intend it to carry:

  1. Take the measured peak kW for the loads the hire set will feed.
  2. Add a margin for motor starting, particularly fire pumps, lifts and large chillers. Starting current can be several times the running current, and a hire set that runs the load but cannot start the fire pump is not adequate.
  3. Convert to kVA using a realistic power factor (0.8 is the usual rating basis).
  4. Choose the next standard hire size above the result, and confirm with the hire company that it can accept the largest single motor start.

Agree who refuels and how many hours the hire set’s tank lasts at the expected load. Typical diesel generator rental costs in India vary with size, duration and location; transport and connection charges weigh heavily on short hires.

Step 5: Plan the connection

The cleanest connection is to a pre-installed changeover point or a spare outgoing way on the main LT panel. If the building has neither, the electrical contractor needs to design a temporary connection, which takes time and may itself need a short shutdown. Questions to settle:

  • Where will the hire set be parked, with access for a truck or crane and enough clearance for exhaust and cooling air?
  • How long are the cables, and what route avoids traffic, water and public areas?
  • Will the hire set connect through the existing ATS/AMF, or through a manual changeover? If manual, who operates it and how quickly?

Step 6: Check compliance of the hire set

The temporary set is a DG set running on your site, so it needs to meet the emission rules that apply in your area. In Delhi NCR and other regions with strict controls, ask the hire company for evidence that the set is CPCB IV+ compliant or fitted with a type-approved emission control device, and check the current local orders. The posts on installing an RECD on a rented diesel generator and DG set emission regulations explain the background, and the CPCB website is the reference for official notifications.

Phase 2: Choosing the Work Window (6 to 3 Weeks Before)

Avoid peak outage seasons

Grid reliability in most Indian cities varies through the year. In north India, outage risk tends to rise in the peak summer months (high demand, transformer failures) and during monsoon storms. Use your DG run-hour history to find the calmest months.

Check GRAP and seasonal restrictions

In Delhi NCR, Graded Response Action Plan stages are typically invoked from October onwards as air quality deteriorates, and DG restrictions tighten as stages escalate. That affects a retrofit in two ways:

  • If your existing DG is not yet compliant, it may be restricted during GRAP stages anyway, so the backup you are trying to preserve may not be usable. In that case, the retrofit itself is the priority and should ideally finish before the season begins.
  • A hire set brought in during GRAP must be one that is permitted to run under the stage in force.

See GRAP stages 1 to 4 and what changes at each level to judge how the timing interacts with your site.

Coordinate with critical loads

Agree the dates with the owners of the critical loads. For a hospital that means the medical superintendent, the ICU and OT in-charges, and biomedical engineering. For an office, IT, security and tenants with server rooms. Ask them:

  • Are there planned activities (surgeries, data migrations, audits, events) that must not coincide with the window?
  • Can non-urgent activity be reduced during the “no backup” hours?

Get the agreed window signed off in writing, with named contacts on each side.

Pick the time of day

The single riskiest period is the changeover itself: from DG out of service to hire set connected, and back again. Schedule these changeovers at the lowest-load, lowest-risk time, which is often early morning on a weekend for offices, or a quieter period agreed with clinical staff for hospitals.

Phase 3: Pre-Work to Minimise Downtime (3 Weeks to 1 Day Before)

Everything that can be done while the DG is still in service should be done before Day 0.

Survey and drawings

Confirm the dimensions, flange sizes and support points on site, and check them against the agreed general arrangement drawing.

Pre-fabrication

Have connecting spools, transition pieces, flanges, supports and brackets fabricated off-site, painted and ready. Lifting arrangements (chain blocks, beams, crane booking) should be confirmed and, for rooftop or basement sets, the route rehearsed.

Trial fits

Where practical, offer up supports and brackets while the DG is still in service, and mark drilling or fixing points. The guide on RECD trial installation acceptance criteria explains how to define what “fits” means.

Reduce or avoid cutting

Depending on the existing exhaust layout and connection type, it may be possible to fit the RECD at an existing flanged joint rather than cutting the pipe, which shortens the work and makes reversal easier if something goes wrong. See can an RECD be installed without cutting the existing exhaust pipe.

Pre-wire the controller

Mount the controller, run cable trays and pull cables before Day 0, leaving only the final terminations to the sensors and DG interface. Check that the controller’s supply is available and correctly protected; the post on RECD controller and heater power supply requirements explains what to confirm.

Connect and test the hire set

Bring the hire set to site at least a day before the window, connect it, and run it on load. Ideally, do a real transfer of the critical loads to it and back while the main DG is still available. This proves the connection, the changeover and the motor-starting capacity while a failure is still only an inconvenience.

Phase 4: The Outage Window (Day 0 to Day N)

Day-by-day plan

A typical sequence for a single set with pre-fabricated parts and good access looks like this. Adjust to your project.

TimeActivityBackup status
Day 0, 06:00Transfer critical loads to hire set; confirm stableHire set
Day 0, 06:30Isolate main DG (lock-out, tag-out); allow exhaust to coolHire set
Day 0, 08:00Remove exhaust section or open flanged joint; lift RECD into placeHire set
Day 0, 13:00Fit connecting pieces and supports; install sensorsHire set
Day 0, 17:00Made-safe point: exhaust closed and supported, DG can run if neededHire set, main DG restorable
Day 1, 08:00Final terminations, controller configuration, insulation workHire set
Day 1, 13:00First run of main DG on hire set’s load bank or site load; leak and back-pressure checksHire set and main DG
Day 1, 16:00Return-to-service checks (see Phase 5)Main DG in auto by end of day

The made-safe point is the most important line in the table. Plan the work so that at the end of each working day, even if the job is not finished, the exhaust is closed, supported and leak-free, and the DG can be started and run in an emergency. Never leave a set overnight with an open exhaust, unsupported weight on the turbocharger or manifold, or disconnected control wiring that would stop it starting.

Without a hire set

If you chose Option C, compress the “no backup” hours into a single block, start early, and keep a crew and all parts ready to restore the DG within an agreed time. Agree a “point of no return” in the schedule: if the job is behind by a certain time, stop, make safe and resume another day rather than push into an unplanned overnight gap.

Phase 5: Return to Service

Before the DG is declared available, work through a written checklist, even if the job ran late.

CheckWhat to confirmSigned by
MechanicalAll flanges tightened to spec, gaskets correct, supports fitted, no load on the engine’s exhaust outletInstaller
Exhaust leaksNo leaks at joints during a run at loadInstaller and DG maintainer
Back-pressureMeasured at load and within the engine maker’s limitInstaller and DG maintainer
Sensors and controllerReadings plausible, alarms reaching the BMS or SMS as designedInstaller and BMS contractor
DG controlsATS/AMF returned to auto, start and transfer testedDG maintainer and electrical contractor
Insulation and guardingHot surfaces insulated or guarded, labels in placeInstaller
HousekeepingTools, debris and temporary supports removed; access routes clearSite facilities
FuelMain DG day tank at normal levelSite facilities
HandoverOperators briefed on new alarms and readingsInstaller
Hire setOnly released after a successful auto-start and transfer of the main DGSite facilities

Hold the hire set for at least a few hours after the main DG goes back into auto, and ideally overnight. If an early problem appears, such as a leak or a sensor fault, you still have cover. Anything left unfinished goes on a punch list with dates; see closing an RECD punch list before handover.

Contingency: If the Grid Fails Mid-Work

Write this plan before Day 0 and brief everyone on site, including security and the hire company.

With a hire set connected

The hire set should pick up the load automatically (if connected through an ATS) or by a quick manual changeover. Work on the main DG continues, because it is isolated. Check the hire set’s fuel against the expected outage length and arrange a top-up.

Without a hire set, before the exhaust is opened

Stop the work, remove the lock-out under the supervision of the authorised person, and return the DG to service. Resume once the grid is stable.

Without a hire set, after the exhaust is opened

This is the scenario the made-safe planning exists for. The options are:

  • If the RECD is already in place and supported, complete the minimum joint work to close the exhaust and run the DG. Controller terminations can wait.
  • If the original exhaust section has been removed and the RECD is not yet fitted, refit the original section (which is why it should be kept on site, not scrapped on Day 0).
  • If neither can be done quickly, fall back to UPS and inverter capacity, shed non-essential loads, and inform the critical-load owners immediately using the agreed phone tree.

Never run the DG with an open or unsupported exhaust inside an enclosed DG room. Diesel exhaust in an occupied or confined space is a serious hazard.

Worked Example: 500 kVA Hospital Annexe (Illustrative)

The figures below are illustrative and show how the steps fit together.

Site: A hospital annexe in Noida with day-care procedures, a small diagnostic lab, a pharmacy and offices. It has one 500 kVA DG set and no second set. The main hospital block is on a separate supply.

Load mapping: The facility team listed the DG’s loads and reviewed three months of load logs.

Load groupPeak kW (measured)Own backup?
Fire pump (jockey and main, main pump 45 kW)50No
Emergency and corridor lighting18Partial (some battery fittings)
Lift (one bed lift)22No
Lab analysers and cold storage40Analysers on UPS (30 min)
Pharmacy refrigeration12No
Procedure rooms (lighting, small equipment)35Some UPS
HVAC for procedure rooms and lab90No
Offices and general areas60No
Total measured peakabout 260 kW (not all coincident at once)

Strategy: Full rental cover (Option A) for the whole outage window. Critical-load-only cover was ruled out because the LT panel could not separate procedure-room HVAC from general HVAC.

Sizing: 260 kW peak ÷ 0.8 power factor ≈ 325 kVA. Allowing for the fire pump’s start while the rest of the load is running, the hire company recommended a 400 kVA set, which it confirmed could accept the 45 kW pump start at the measured base load.

Connection: The LT panel had a spare 630 A outgoing way. The electrical contractor fitted a temporary manual changeover with interlock, and cabled to a hire set parked in the service yard, about 25 metres away.

Window: Outage history showed March and early April with the fewest long outages. The project was scheduled for a Saturday and Sunday in March, after GRAP restrictions had eased, with procedures booked lighter on that Saturday. The hire set was confirmed CPCB IV+ compliant.

Pre-work: Over the previous two weeks, the installer surveyed, fabricated the transition spool and supports, offered up brackets, pulled cables to the controller location and confirmed controller power. On Friday, the hire set was delivered, connected and run on the annexe load for two hours, including a fire pump start test, then the load was transferred back to the main DG.

Outcome: Main DG isolated at 06:30 Saturday; RECD fitted and exhaust closed by 16:30 (made-safe point). Terminations, insulation and checks on Sunday morning, a load run at 12:00 with back-pressure within the engine maker’s limit, and return to auto at 15:00. The hire set stayed until Monday 10:00.

Backup gap: Zero hours without a running source available, apart from two planned manual changeovers of about 3 to 4 minutes each, during which the analysers and some procedure-room equipment rode through on UPS. During the weekend, the grid failed once for 40 minutes on Saturday afternoon. The hire set carried the load and work continued.

Frequently Asked Questions

How long is a DG set usually out of service for an RECD retrofit?

For a single set with good access and pre-fabricated parts, the main DG is often out of service for one to two working days, with the exhaust closed and the set restorable at the end of the first day. Difficult access, rooftop lifts or unexpected exhaust modifications can extend this. Good pre-work is the biggest factor.

Can any of the work be done with the DG still in service?

Yes. Mounting the controller, running cable trays and fitting brackets away from hot surfaces can usually be done beforehand. Exhaust work itself needs the DG isolated, locked out and cool.

What if the grid fails and the hire set does not start?

That is why the hire set should be run on load and tested with a real transfer before Day 0, and why every working day should end at a made-safe point. If both fail, fall back to UPS capacity, shed non-essential loads and follow the agreed contingency plan to restore the main DG.

Should we retrofit before or after the GRAP season?

In Delhi NCR, aim to complete the retrofit before GRAP restrictions typically begin in autumn, so the DG is compliant when it is most likely to be scrutinised. If that is not possible, plan the window for after restrictions ease, and make sure any hire set is permitted to run under the stage in force.

Related Reading

Plan Your Retrofit Around Your Backup Needs

A well-planned retrofit keeps your building protected from the first survey to handover. Aceget supplies CPCB type-approved Retrofit Emission Control Devices for DG sets from 25 kVA to 2500 kVA, and can work with your facility and electrical teams on timing and installation planning. Review our certifications or contact our team to discuss your site.



1 Comment

  • […] The cheapest margin is choosing a window with fewer outages and less regulatory pressure. In Delhi NCR, GRAP restrictions usually tighten from October into the winter, and some DG use is restricted at the higher stages. See GRAP Stage 1 to 4: what changes at each level. Summer brings peak outages and cooling load. Late winter to early spring often balances both. For more temporary cover options, see how to preserve backup power during an RECD retrofit. […]