Sequencing RECD Installations on an N+1 Generator System

If your site runs on an N+1 generator system, you already paid for one spare set of capacity. That spare is what lets you lose a generator during an outage and keep the critical load running. An RECD retrofit quietly spends that spare. The moment the first set is isolated for fabrication and fitting, the system becomes N+0, and one more failure is the difference between a routine outage and a site-wide blackout.

This post works through RECD installation on N+1 generators as a series of scenarios, each a decision point the facility manager, DG maintainer and RECD supplier will face in roughly that order. It ends with a worked example for a four-set system, a week-by-week sequence and a go/no-go checklist.

The principle running through all of it is simple: take one set out at a time, prove it is healthy before it rejoins the bus, and never start the next set until the last one is fully back in service.

The Starting Scenario: Four Sets, One Bus, One Deadline

Picture an illustrative campus in Delhi NCR. It has four 750 kVA DG sets synchronised onto a common bus through a sync panel with a power management system (PMS). An automatic transfer switch (ATS) arrangement moves the critical load to the DG bus when the grid fails. The sets are a few years old, and the site’s compliance register shows that an RECD must be fitted on every set before the next enforcement window.

The site cannot shut down. The DG-backed critical load (servers, cold rooms, process cooling, fire and life-safety systems) is 1,600 kW at its design peak, of which about 100 kW (support-area comfort cooling and some lighting) has been agreed as deferrable in an emergency, and outages of 20 minutes to several hours happen most weeks in summer. Everyone agrees the retrofit must happen. The question is how to do it without gambling with the backup power that the generators exist to provide.

What N+1 Actually Protects

N is the load, +1 is the insurance

“N” is the number of sets needed to carry the critical load on their own. “+1” is one additional set that covers the failure of any single unit. On our illustrative campus, three sets can carry 1,600 kW, so N is 3 and the fourth set is the redundancy.

N+1 protects against three things:

  • A set that fails to start when the grid drops, which is the most common failure in standby duty.
  • A set that trips while running, for example on high coolant temperature, low oil pressure or overspeed.
  • Planned maintenance on one set, with the others still able to carry the full load.

What N+1 does not protect

N+1 does not cover two sets being unavailable at once, which is exactly what happens if one set is out for installation and another fails during an outage. Nor does it cover common-mode failures such as a sync panel fault or a PMS setting that refuses to close the bus, and retrofit work touches exactly those systems.

So the planning goal is not “keep N+1 during the retrofit” in the strict sense. With one set physically out, you cannot. The goal is to restore an equivalent level of protection with temporary measures, and to shorten and control the period when protection is reduced.

Scenario 1: The Margin Check Before Anything Is Unbolted

The first meeting should not be about the RECD at all. It should be about arithmetic. Before any set is isolated, calculate what the remaining sets can carry and what happens if one more fails.

Step 1: Convert kVA to usable kW

DG sets are rated in kVA, but the load is measured in kW. At the standard 0.8 power factor, a 750 kVA set delivers 750 × 0.8 = 600 kW. If you are unsure how your nameplate figures translate, see how to read a generator’s kVA and kW rating. Use the rating that matches your duty (standby or prime).

Step 2: Define the load you are protecting

Use the design peak for the critical load, not an average. Then cross-check it against real outage data from your DG load logs. If the logs show a peak of 1,480 kW over the last 90 days and the design figure is 1,600 kW, plan on 1,600 kW. The retrofit window may coincide with a hotter week or a new load nobody told you about.

Step 3: Set a planning cap

Most maintainers do not want sets running near 100% of rating for hours during an emergency. A common planning cap is 85% of rated kW. It leaves room for motor starting, step loads and a slightly derated set on a hot day. Agree the cap with your DG maintainer before you start.

Step 4: Calculate the margin in each condition

The table below is illustrative and uses the campus figures.

ConditionSets availableAvailable kWLoad (kW)LoadingWithin 85% cap?
Normal, all four sets42,4001,60066.7%Yes
Normal, one set fails31,8001,60088.9%No, but within rating
Retrofit, one set out31,8001,60088.9%No, but within rating
Retrofit, one set out, one more fails21,2001,600133.3%No, 400 kW short

Two things stand out. First, even with one set out and no other failure, the remaining three sets run at 88.9%, above the 85% cap. The cap allows 0.85 × 1,800 = 1,530 kW, so the site is 70 kW over it. Second, if one more set fails during the retrofit, the two survivors face 1,600 kW with only 1,200 kW available. That is a 400 kW shortfall, and the bus will collapse or shed load uncontrollably.

That 400 kW drives every other decision: the site needs about 400 kW of extra capacity, load it can drop on purpose, or a mix of both.

Scenario 2: Choosing the Pilot Set

The first set you retrofit is a trial. Everything you learn on it (fabrication fit, actual back-pressure, controller wiring, sensor readings, how long the work really takes) shapes the next three. So pick the first set deliberately rather than just starting with DG-1.

Good candidates for the pilot set usually have most of these features:

  • Best access. Nearest the door, the crane point or the louvre opening, so fabrication delays are least likely.
  • Lowest priority in the PMS start order, so the system behaves most normally while it is out.
  • Typical engine and exhaust layout, so lessons transfer to the other sets. A set with an odd exhaust route teaches you about that set only.
  • Good engine condition. A set with existing smoke or oil-carryover issues will confuse the RECD results. If there is doubt, read whether to overhaul the engine before fitting an RECD.

Treat the pilot as a formal trial installation with acceptance criteria. Write down in advance what “pass” means: back-pressure within the engine maker’s limit at the test load, no exhaust leaks, sensor values plausible, controller alarms tested and cleared, synchronisation and load sharing normal. If the pilot fails any of these, stop and fix the design before touching set two.

After the pilot set returns, many sites hold it in service for a week before starting the next one. That hold week shows how the RECD behaves across real outages, real starts and real load swings. It costs time but often saves rework on three more sets.

Scenario 3: The Sync Panel and ATS Conversation

The crew works on the exhaust, but the biggest risk often sits in the sync panel. When a set is isolated, the PMS and ATS logic must know it is gone. If they still count it as available, the system will make decisions based on 2,400 kW of capacity it does not have.

What to agree with the panel builder or electrical contractor

  1. Remove the set from the available-sets list. Put the set’s controller in Off or Maintenance mode, rack out or lock open its generator breaker and apply lockout and tagging. Confirm on the PMS screen that it shows as unavailable, not just stopped.
  2. Check the start priority order. If the isolated set was first in the lead order, the PMS must now start another set as lead. Confirm which set takes over and that it starts and closes onto the dead bus correctly.
  3. Review bus-ready conditions for the ATS. Some schemes transfer load only when a set number of generators are on the bus. If that threshold is “three sets online”, the ATS may wait for a set that will never come. Agree the temporary threshold and the load-shed step that goes with it.
  4. Review load-dependent start and stop. With three sets, cycling may increase. Confirm stop delays are long enough to avoid rapid cycling.
  5. Record every setting change. Write the original value, the temporary value, who changed it and when. Every temporary change must be reversed when the set returns. A change log is the only reliable way to make sure nothing is left in the wrong state.

RECD controller wiring into the panel

If the RECD controller will send alarm or status signals to the sync panel or the BMS, the wiring for each set is usually done while that set is isolated. Decide early which signals go where and what each one should do. Most RECD alarms should raise a warning rather than trip a set during an outage. Engine-protection limits, such as back-pressure above the engine maker’s maximum, are the exception, and that response is decided with the DG maintainer and the engine maker, not by the RECD supplier alone. For the full approach, see RECD alarm vs generator trip.

Scenario 4: Temporary Measures When the Margin Is Thin

The margin check showed a 400 kW shortfall under a second failure and a 70 kW breach of the planning cap even with no further failure. There are three main levers to fix this.

Lever 1: A temporary rental set

A rental DG set restores capacity while one permanent set is out. It is rarely synchronised into an existing PMS, because controllers and protection settings seldom match. More often, a temporary changeover lets it feed a defined feeder group on its own.

Plan for:

  • Rating and fuel. Size it to carry the chosen feeder group at a comfortable loading, and arrange refuelling for the full retrofit period.
  • Connection point. A temporary changeover with proper protection, earthing and cable routes, installed and tested before the first permanent set is isolated.
  • Its own emissions status. A rental set running for several weeks in NCR may itself need to be compliant. Check this with the rental company and read whether an RECD can be fitted on a rented DG set.
  • Cost. Rental charges, transport, cabling and fuel all add up, so budget for the whole retrofit period.

Lever 2: A load shedding plan

A load shedding plan defines which loads will be dropped, in what order, and how. It should be written, tested and known to every shift. Typical candidates are comfort cooling in non-critical areas, some lighting circuits, EV chargers, workshop loads and non-urgent pumps. Each item needs a named breaker or PMS shed step, its approximate kW and the person allowed to drop it.

Do not rely on a plan that has never been exercised. Run a shed test during a grid-on period and measure how many kW actually come off. Paper estimates are often optimistic.

Lever 3: Timing

The cheapest margin is choosing a window with fewer outages and less regulatory pressure. In Delhi NCR, GRAP restrictions usually tighten from October into the winter, and some DG use is restricted at the higher stages. See GRAP Stage 1 to 4: what changes at each level. Summer brings peak outages and cooling load. Late winter to early spring often balances both. For more temporary cover options, see how to preserve backup power during an RECD retrofit.

Scenario 5: Testing Each Set Before It Rejoins the Bus

A set is not “back” when the crew packs up. It is back when it has proved, under load, that it can do its job in the synchronised system. Testing after each set should cover four layers.

Layer 1: Mechanical and exhaust checks

  • Visual inspection of every joint, flange and gasket, and a leak check at running temperature.
  • Supports, expansion joints and clearances to cables and structures.
  • Back-pressure measured at the test load and compared with the engine maker’s limit. The background is in how exhaust back-pressure affects a DG set.

Layer 2: Standalone load test

Run the set on its own at a meaningful load, ideally on a load bank at 75% or more of rating. A freshly fitted RECD tested only at light load tells you little, because exhaust temperature and back-pressure both rise with load. Record exhaust temperature upstream and downstream, back-pressure, engine parameters and any controller alarms. Let the set reach stable temperatures before you record anything.

Layer 3: Synchronisation and load sharing

Run a synchronised test with at least one other set. Confirm the set synchronises, closes onto the bus and shares kW within the site’s normal tolerance. The RECD should not change electrical load sharing, because governors control kW, but its back-pressure can shift fuel use and exhaust temperature. Note these against the other sets.

Layer 4: Controls and alarms

Test each RECD signal to the panel or BMS end to end. Force an alarm and confirm it appears with the right text and priority, and does not trip the set unless agreed as an engine-protection limit. Then restore all PMS and ATS settings from the change log and confirm on screen that the set shows as available.

Only after all four layers pass, and the paperwork is signed, does the next set become eligible for isolation.

The Worked Example in Full (Illustrative)

Here is the complete plan for the illustrative campus: four 750 kVA sets (600 kW each), a 1,600 kW critical load and an 85% planning cap. All figures are illustrative and should be replaced with your own.

Temporary cover design

The site hires one 750 kVA rental set (600 kW) and connects it through a temporary changeover to a 480 kW feeder group that serves one block’s process cooling. It also prepares a tested load-shed step for the 100 kW of deferrable load, all of which sits on the permanent bus.

Condition during retrofitAvailable kWLoad (kW)LoadingWithin 85% cap?
Three permanent sets on bus1,8001,600 − 480 = 1,12062.2%Yes
Rental set on its feeder group60048080.0%Yes
Second permanent set fails, before shedding1,2001,12093.3%No, but within rating
Second permanent set fails, after 100 kW shed1,2001,02085.0%Yes, at the cap
Rental set fails, feeder group moved back to bus1,8001,60088.9%No, but within rating

Check the arithmetic: 1,120 ÷ 1,800 = 0.622; 480 ÷ 600 = 0.800; 1,120 ÷ 1,200 = 0.933; 1,020 ÷ 1,200 = 0.850; 1,600 ÷ 1,800 = 0.889.

With the rental set and the shed step, the site can survive a second permanent set failure, which restores the protection N+1 normally gives. If the rental set fails, the feeder group can be switched back to the bus manually, and the three permanent sets still carry the full load.

Week-by-week sequence

The pilot set is DG-3. It has the best crane access, is last in the PMS start order, and its exhaust layout matches DG-1 and DG-2. DG-4 has a longer exhaust run and goes last, when the crew has the most experience.

WeekActivitySets on busKey outputs
0Survey all four sets, freeze GA drawing, mobilise and test rental set, test load-shed step, record baseline back-pressure4Margin calculation signed, change log opened
1DG-3 (pilot): isolate Monday, install Tuesday to Thursday, standalone load test Friday, sync test and return Saturday3, then 4Trial acceptance record for DG-3
2Hold week: DG-3 in normal service, review outage data, lessons-learnt meeting, adjust design for remaining sets4Go/no-go decision for DG-1
3DG-1: isolate, install, test, return3, then 4Acceptance record for DG-1
4DG-2: isolate, install, test, return3, then 4Acceptance record for DG-2
5DG-4: isolate, install (longer exhaust run allows one extra day), test, return3, then 4Acceptance record for DG-4
6Full system test with all four sets, restore all settings, demobilise rental set, close punch list4Handover pack

The rental set stays connected from Week 0 to Week 6. No two permanent sets are ever out together, and each return is verified before the next isolation. If a set overruns (for example, a flange needs re-machining), the next set waits. The schedule bends; the rule does not.

For realistic durations per set, see the RECD installation timeline.

Go/No-Go Checklist Before Each Set Comes Out

Run this checklist at a short meeting on the morning of each isolation. If any answer is “no”, the set stays in service.

Capacity and cover

  • Is the previous set fully returned, tested and showing as available on the PMS?
  • Are all other permanent sets healthy, with no open alarms or deferred faults?
  • Is the rental set running-tested this week, fuelled and connected to its feeder group?
  • Has the load-shed step been tested, and does the shift know who triggers it?
  • Does the margin calculation still hold, given any new load added since Week 0?

External conditions

  • Are the weather forecast and grid supplier notices free of storms, heat waves or planned shutdowns?
  • Does the current GRAP stage or any local order restrict DG use for testing or the rental set?

Work readiness

  • Are all RECD parts, gaskets, supports and fasteners for this set on site and checked?
  • Is the crane, lifting plan and access route confirmed?
  • Are permits to work, hot-work permits and lockout procedures in place?
  • Are the sync panel and ATS changes for this set written in the change log, ready to apply?
  • Is the test load (load bank or bus load) arranged for the return test?

People

  • Are the DG maintainer’s engineer and the PMS engineer available for isolation, setting changes and the sync test?
  • Has every shift been briefed on the reduced-capacity condition and the shed plan?

FAQ

Can we install RECDs on two N+1 sets at the same time if the work is quick?

It is not recommended. Even on a fast job, two sets out at once usually leaves the site below N, which means the critical load is not covered even without any further failure. The time saved is small compared with the risk. Do one set, return it, then start the next.

Does the RECD affect load sharing between synchronised sets?

Not directly. Electrical load sharing is controlled by the governors and the PMS, so each set still carries its kW share. The RECD adds some back-pressure, which can raise exhaust temperature and fuel use slightly. That is why you compare these values across sets after each return.

Do we always need a rental set?

No. If your margin with one set out stays within your planning cap, and a second failure can be handled with a tested load-shed plan, you may not need one. Run the arithmetic first. If the second-failure shortfall is larger than the load you can safely drop, a rental set or another form of temporary capacity is the safer option.

What if the pilot set fails its acceptance tests?

Stop the sequence. Keep the remaining sets untouched, find the cause with the supplier and the DG maintainer, and correct the design. Restart only when the pilot passes. This is the main reason to run a pilot in the first place.

Plan Your N+1 Retrofit With Aceget

Aceget supplies CPCB type-approved Retrofit Emission Control Devices for DG sets from 25 kVA to 2500 kVA. You can review our certifications and the CPCB’s own guidance on the CPCB website, and read about filter regeneration behaviour on DieselNet. When you are ready to plan the sequence for your own site, contact our team with your set ratings, load data and outage history.