Most Retrofit Emission Control Device (RECD) projects end with a commissioning visit, and most DG sets get a load-bank test at some point in their life. On many sites these two events happen weeks apart, organised by different people, with different contractors and different paperwork. That is a missed opportunity. A load bank gives you exactly what RECD commissioning needs: hot exhaust, steady and repeatable load points, and enough running time to watch the device settle.
This guide treats the combined test day as a sequence of load steps. At each step there is a generator check and an RECD check, recorded on the same sheet at the same timestamp. The result is one mobilisation, one data pack and a much clearer picture of how the generator and the RECD behave together.
Engine-protection limits and decisions remain with the DG maintainer and the engine maker throughout.
Why Combine the Two Tests?
Commissioning must prove the RECD is installed correctly, its sensors work and it does not push the engine outside its limits. A cold engine idling in the DG room proves very little.
Hot exhaust on demand
A particulate filter or catalytic element behaves differently at 200 °C than at 450 °C. Differential pressure across the device, outlet temperature, and the conditions for passive regeneration all depend on exhaust temperature. Building load on a Sunday afternoon may sit at 20–30% of rating, which is rarely enough. A load bank lets you take the set to 75% and 100% and hold it there. Our guide on warm-up time for RECD testing explains why readings taken before the system stabilises are misleading.
Repeatable load points
If you want to compare before and after readings, or compare this year with next year, the load has to be the same. Building load drifts every minute. A load bank set to 200 kW stays at 200 kW. This is the core argument in why generator load must be matched for RECD comparison tests.
One mobilisation
Load banks are hired by the day, often with a technician and a truck. The RECD supplier’s engineer, the DG maintainer and perhaps a third-party emissions tester all need to be present. Bringing them together once costs less than separate visits, and everyone sees the same data at the same moment.
Choosing and Sizing the Load Bank
Resistive load banks
The most common hire unit in India is a resistive load bank: banks of heating elements cooled by fans. It draws real power only, so it runs at unity power factor (PF 1.0). That matters because a generator’s kVA rating assumes a PF of 0.8.
A 500 kVA set at 0.8 PF is rated at 400 kW. A resistive bank set to 400 kW loads the engine to its full kW rating, which is what the RECD cares about, since exhaust flow and temperature follow engine power. It does not load the alternator to full kVA, which is usually acceptable for RECD commissioning. The rule is simple: match load in kW, not kVA. Our explainer on how to read generator kVA and kW ratings covers the conversion in more detail.
Resistive-reactive load banks
A resistive-reactive (RL) load bank adds inductive elements so you can test at 0.8 PF. On a 500 kVA set, 400 kW plus 300 kVAr gives 500 kVA (since 400² + 300² = 500²). This tests the alternator, AVR and cabling at full current as well as the engine. It costs more, and for RECD purposes engine kW is still what drives exhaust conditions.
Sizing checks before hire
- Load bank capacity should be at least the set’s kW rating, with some margin, so it does not run flat out.
- Step resolution matters. A bank that only switches in 100 kW blocks cannot give you a clean 25% step on a 250 kW set.
- Confirm voltage (415 V three-phase is typical), frequency and connection method (cam-lock, lugs or busbar).
- Read kW from both the bank’s meter and the generator controller, and note any difference.
Before the Test Day
A combined day only works if the preparation is shared. Agree these items at least a week ahead:
- Test plan and step table. Circulated to all parties, with target kW, hold times and what each person records.
- OEM back-pressure limit. The engine maker’s maximum allowable exhaust back-pressure, in writing, with the measurement point it refers to. The DG maintainer usually holds this. Background is in how exhaust back-pressure affects a DG set.
- Isolation of building load. Decide whether the set will be fully isolated from the building or whether the test will run with the mains supply healthy and the DG breaker feeding only the load bank.
- Sensor calibration records. The RECD’s pressure and temperature sensors should have current certificates. See installed RECD sensor calibration documentation.
- Fuel. Enough for the full test plus a margin. Running out mid-soak wastes the whole sequence.
- Time sync. Set the generator controller, RECD controller, any data logger and everyone’s phones to the same clock (IST), so readings line up later.
The Combined Test Sequence
Each step has a load target, a minimum hold time and RECD checks attached. Do not move on until the step is stable, even if the clock says you can.
Step 0: Pre-start checks (engine off)
- Visual inspection of the RECD, supports, bellows and flanges. Look for missing bolts, gasket misalignment and cables touching hot surfaces.
- Confirm the RECD controller is powered and showing healthy status.
- Record zero readings from the differential pressure sensor with the engine off. A non-zero reading at rest points to a sensor offset or a blocked tapping.
- Check the load bank position, cable route and earthing (see the safety section below).
Step 1: Start and idle warm-up (no load)
- Start the set, confirm normal oil pressure and coolant temperature.
- Run at no load or light load for 5–10 minutes as the DG maintainer advises.
- RECD check: controller recognises engine running, no alarms, pressure readings begin to rise from zero.
Steps 2 to 5: 25%, 50%, 75% and 100% load
At each step, hold until exhaust inlet temperature changes by less than about 5 °C over five minutes, then take the full reading set (ΔP across the device, total back-pressure, inlet and outlet temperature, controller status and opacity if a meter is on site).
| Step | Typical minimum hold | Extra RECD focus |
|---|---|---|
| 25% | 15–20 min | First stable baseline; ΔP should be low and steady |
| 50% | 20 min | ΔP should rise roughly in line with exhaust flow, not jump |
| 75% | 20–30 min | Most representative running point; good for witnessed opacity or PM readings |
| 100% | 30 min | Total back-pressure versus the OEM limit, the key number of the day |
Step 6: Soak and regeneration observation
- Hold at a high load (often 75–100%) for an extended period, usually 45–90 minutes.
- RECD check: watch ΔP trend and outlet temperature for signs of passive regeneration. Record regeneration status from the controller if it reports one.
Step 7: Step down and cool-down
- Reduce load in steps, then run at no load for the cool-down period the DG maintainer specifies before shutdown.
- RECD check: confirm readings fall back smoothly, no alarms on shutdown, controller logs the run end correctly.
What to Record at Each Step
Use one sheet, one row per reading, with a timestamp. Taking two or three readings per step (at the start of hold, mid-hold and end of hold) shows whether the step really stabilised.
| Parameter | Source | Why it matters |
|---|---|---|
| Time (IST) | Synchronised clock | Lines up all other records |
| Load (kW) | Generator controller and load bank meter | Confirms the step is what it should be |
| Power factor | Generator controller | Confirms resistive (1.0) or RL (0.8) test |
| ΔP across RECD | RECD sensor | Indicates loading of the filter element |
| Total back-pressure | Tapping at the engine outlet | Compared with the OEM limit |
| Inlet temperature | RECD sensor | Shows exhaust conditions entering the device |
| Outlet temperature | RECD sensor | Helps spot regeneration and sensor faults |
| Regeneration status | RECD controller, if available | Confirms what the controller thinks is happening |
| Opacity or PM | Portable meter or test lab | Evidence of emission performance |
| Alarms and events | Both controllers | Anything unusual, with time |
First, ΔP and total back-pressure are not the same thing. ΔP is the drop across the RECD alone; total back-pressure at the engine outlet includes the silencer, pipework and RECD together. The OEM limit applies to the total. Our article on comparing RECD pressure readings at different generator loads explains how the two relate. Second, if opacity readings are taken, note the measurement method and units every time; a percentage opacity and a light absorption coefficient (m⁻¹) cannot be compared directly.
Back-Pressure at Full Load Versus the OEM Limit
Every engine has a maximum allowable exhaust back-pressure. Above it, the engine breathes poorly: exhaust temperatures rise, fuel consumption rises, turbochargers work harder and power can drop. A retrofit adds resistance to the exhaust path, so commissioning must show that total back-pressure at full load stays within the limit with a sensible margin.
A few rules make this check meaningful:
- Measure at the point the OEM limit refers to. Usually this is close to the turbocharger outlet or exhaust manifold. A reading taken after the RECD tells you nothing about what the engine sees.
- Measure at full rated kW. Back-pressure rises steeply with flow. A reading at 60% load can look comfortable and still be over the limit at 100%.
- Record the filter condition. A brand-new filter is at its cleanest. The margin you see today will shrink as soot and ash build up between regenerations and services. A margin of only a few per cent at commissioning leaves little room for normal loading.
- Let the DG maintainer judge. The RECD supplier reports the reading; the DG maintainer and engine maker decide whether it is acceptable for the engine.
If the full-load reading is close to or above the limit, stop, reduce load and investigate before continuing. Typical causes include an undersized connection, a crushed bellows, a blocked tapping or a silencer that was already restrictive before the retrofit.
The Regeneration Observation Run
Many RECDs rely on passive regeneration: when exhaust temperature is high enough for long enough, collected soot oxidises and ΔP falls or stops rising. Sets that run lightly in daily use may rarely see these conditions. A load bank soak is a chance to see the mechanism working on your site, with your engine and your fuel. DieselNet’s overview of DPF regeneration covers the chemistry in more depth.
During the soak:
- Record ΔP every 5–10 minutes. A plateau or gentle fall at constant load suggests soot is being burned as fast as, or faster than, it is collected.
- Record outlet temperature alongside inlet temperature. During active soot oxidation, outlet temperature may run close to or slightly above inlet.
- Note controller regeneration status, if the controller reports one, and the time it changes.
Our guide to RECD testing during regeneration and what to record also explains why emission readings taken mid-regeneration should be labelled separately. A device carrying some soot from light-duty running is useful here: the soak then shows it cleaning itself.
Safety on a Combined Test Day
A load bank converts hundreds of kilowatts into heat. Combined with hot exhaust and temporary cabling, the site needs more care than a routine DG run.
Load bank placement
- Place the bank outdoors or in a well-ventilated area, on firm, level ground.
- Keep it clear of the RECD outlet and the generator’s air intake. Hot load-bank air drawn into the engine raises intake temperature and distorts readings. Hot exhaust drawn into the load bank fans affects its cooling.
- Keep it away from the building’s fresh air intakes.
Hot air discharge
- Most banks discharge vertically or horizontally at high temperature. Mark a keep-clear zone and point the discharge away from people, vehicles, vegetation, cables and building facades.
- Check that nothing combustible sits within the discharge path.
Cabling
- Size temporary cables for the full test current. For a 400 kW resistive test at 415 V, current is about 557 A per phase (400,000 ÷ (1.732 × 415)). An RL test at 500 kVA raises that to about 696 A.
- Route cables away from the exhaust line and the RECD body. The principles in RECD cable routing near hot exhaust lines apply to temporary cabling too.
- Protect cable runs across walkways and lock off the connection point.
- Confirm earthing of the load bank and the generator before energising.
People and access
- Hearing protection near the generator and load bank fans.
- Heat-resistant gloves for anyone touching sensor tappings or flanges.
- Only one person gives load change instructions.
Roles on the Day
Unclear roles cause the classic problems: two people adjusting load, readings taken at the wrong moment, nobody watching coolant temperature.
| Role | Typical party | Responsibilities |
|---|---|---|
| Test lead | Facility engineer or consultant | Owns the plan, calls each step, decides when to pause |
| Load bank operator | Load bank hire company or electrical contractor | Sets kW steps on instruction, watches load bank alarms |
| Engine and generator | DG maintainer | Watches engine parameters, holds authority to stop the engine for protection |
| RECD readings | RECD supplier’s engineer | Records ΔP, temperatures, controller status; checks sensors |
| Emissions measurement | Third-party tester, if engaged | Takes opacity or PM readings at agreed steps |
| Recorder | Any one nominated person | Keeps the master sheet, timestamps every reading |
| Safety | Site EHS | Keep-clear zones, permits, PPE, fire extinguishers in place |
The DG maintainer’s authority to stop the engine overrides the test plan. Say so at the morning briefing. For a wider view of responsibility splits, see customer and installer responsibilities in an RECD project.
Worked Example: A 500 kVA Set Commissioned with a Resistive Load Bank
Illustrative only. The readings below are invented to show how a step table works. They are not test results for any specific engine or RECD. Your OEM limit and expected values will differ.
The setup
- Generator: 500 kVA at 0.8 PF, so 400 kW rated (500 × 0.8 = 400).
- Load bank: 500 kW resistive, unity PF, switchable in 25 kW blocks.
- OEM maximum back-pressure (illustrative): 7.5 kPa at the turbocharger outlet.
- RECD newly fitted, light soot loading from two weeks of building-load running.
The step plan
| Step | Target load | kW | Minimum hold | Clock (IST) |
|---|---|---|---|---|
| Warm-up | No load | 0 | 10 min | 10:00–10:10 |
| 1 | 25% | 100 | 20 min | 10:10–10:30 |
| 2 | 50% | 200 | 20 min | 10:30–10:50 |
| 3 | 75% | 300 | 30 min | 10:50–11:20 |
| 4 | 100% | 400 | 30 min | 11:20–11:50 |
| Soak | 75% | 300 | 60 min | 11:50–12:50 |
| Cool-down | No load | 0 | 10 min | 12:50–13:00 |
Total running time is 180 minutes (10 + 20 + 20 + 30 + 30 + 60 + 10). The holds are minimums; if a step is not stable, it runs longer and the clock shifts.
Illustrative readings at end of each hold
| Step | kW | PF | Inlet temp (°C) | Outlet temp (°C) | ΔP RECD (kPa) | Total back-pressure (kPa) | Opacity (%) |
|---|---|---|---|---|---|---|---|
| 25% | 100 | 1.0 | 230 | 215 | 1.1 | 2.0 | 0.9 |
| 50% | 200 | 1.0 | 335 | 320 | 2.0 | 3.4 | 0.7 |
| 75% | 300 | 1.0 | 420 | 410 | 2.9 | 4.7 | 0.6 |
| 100% | 400 | 1.0 | 495 | 490 | 3.7 | 5.9 | 0.6 |
Reading the results
Back-pressure. At 100% load, total back-pressure is 5.9 kPa against an OEM limit of 7.5 kPa. The margin is 1.6 kPa (7.5 − 5.9), which is about 21% of the limit (1.6 ÷ 7.5 = 0.213). The DG maintainer judges this acceptable for a new installation and notes that it should be re-checked after the first service interval.
ΔP trend. ΔP roughly tracks load: from 1.1 to 3.7 kPa as load goes from 100 to 400 kW. Nothing jumps out of line.
Temperatures. Outlet temperature trails inlet by 15 °C at low load and only 5 °C at full load, as expected once the device body heats through.
Soak. During the 60-minute soak at 300 kW, ΔP readings taken every 10 minutes went 2.9, 2.9, 2.8, 2.7, 2.7, 2.6 kPa. At constant load and temperature, a fall of 0.3 kPa (2.9 − 2.6) over the hour suggests the light soot load from building running was being oxidised. The controller showed its regeneration indicator active from about 12:05. Outlet temperature rose from 410 °C to 418 °C during the same period.
Opacity. Readings are low throughout. For a formal before and after performance claim, the team would rely on the planned laboratory test rather than a portable meter; see RECD emissions test before and after: planning and calculation.
What went into the record
The test lead signs off the step table, the DG maintainer signs the back-pressure result, and the RECD engineer signs the sensor and controller checks. One open item is logged: the outlet temperature sensor cable needs an extra clip near the flange.
The Data Pack
The test day is only as useful as the record it leaves. Assemble the data pack within a few days, while memories are fresh.
Contents
- Test plan as issued, with any changes made on the day marked.
- Master reading sheet, every row timestamped in IST. If you export data files, ISO 8601 date-time format avoids confusion between DD/MM and MM/DD.
- Controller exports from both the generator controller and the RECD controller, if they provide logs.
- Load bank report, showing kW steps and duration.
- OEM back-pressure limit, with the source document.
- Back-pressure result, signed by the DG maintainer.
- Sensor calibration certificates for all instruments used.
- Emissions test report, if a laboratory or third party took measurements.
- Photographs of the installation, sensor positions, the load bank set-up and the controller screens at full load.
- Open items list with owners and dates.
- Sign-off sheet from each party.
Why it matters later
When the SPCB asks for evidence, or the RECD shows a higher ΔP two years later, this pack is the baseline. It also feeds the site acceptance test record covered in factory acceptance vs site acceptance tests for RECD projects.
Frequently Asked Questions
Should we use a resistive or a resistive-reactive load bank?
For RECD commissioning, a resistive bank is usually enough because the engine’s kW output drives exhaust flow and temperature. Choose an RL bank if the DG maintainer also wants to test the alternator and AVR at full kVA and 0.8 PF. Either way, match your load steps in kW.
How long should each load step last?
Long enough for exhaust temperature and ΔP to stabilise. As a starting point, 15–20 minutes at low loads and 30 minutes at high loads, but use the stability rule (little change over five minutes) rather than the clock alone.
What if back-pressure exceeds the OEM limit at full load?
Reduce load straight away and let the DG maintainer decide whether to stop. Then investigate: check the measurement point, tappings, bellows, silencer and pipework. Do not accept the installation until the cause is found and the reading is back within the limit with a reasonable margin.
Will the regeneration soak clean a heavily loaded filter?
A soak can help passive regeneration, but it is not a cure for a filter that is heavily loaded with ash or has been neglected. If ΔP stays high or keeps rising during the soak, follow the RECD supplier’s maintenance guidance. Background on ash is in DieselNet’s note on DPF ash.
Related Reading
- RECD Fitment and ATS Testing: What Should Facility Teams Coordinate?
- Scheduling RECD Work Around a Factory’s Annual Shutdown
- Witnessed RECD Performance Demonstration
- RECD Trial Installation Acceptance Criteria
- RECD Fitment on Trailer-Mounted Generators: Transport and Setup Checks
Plan Your Commissioning with Aceget
Aceget supplies CPCB type-approved Retrofit Emission Control Devices for DG sets from 25 kVA to 2500 kVA. If you are planning a load-bank test day and want the RECD commissioning built into it, our team can help you work through the step plan, the readings to take and the documents to keep. You can review our certifications, check the regulatory background on the CPCB website, or contact our team to discuss your site.
[…] Coordinating RECD Commissioning with Generator Load-Bank Testing […]
[…] some tests or running them on load, perhaps with a load bank, gives the device a fair chance. Our RECD commissioning load bank testing plan shows how load banks are used during commissioning; the same approach can support periodic […]