Fitting a Retrofit Emission Control Device to one generator owned by one company is a fairly contained job. The owner decides, pays, signs the purchase order and keeps the records. Things get far more complicated in a building where the generators belong to different people. A Gurugram office tower may have landlord-owned sets serving common areas, a bank on the ground floor with its own 250 kVA set, and a food court operator with another. A residential complex may have sets owned by the RWA but operated by a facility management company that reports to a builder who has not fully handed over. Each party has a different budget cycle, a different appetite for risk and a different idea of who should pay.
The technical work in these buildings is no harder than anywhere else. What fails is coordination. Roof access is refused because a lease does not mention it, a shared chimney cannot be modified until three parties agree, or one tenant’s set is left out and the whole building looks non-compliant during an inspection. This guide is built around two tools that prevent those failures: a stakeholder map, which tells you who is involved and what they control, and a governance model, which tells you how decisions get made, paid for and recorded. An illustrative worked example with a cost-allocation table follows at the end.
Part 1: The Stakeholder Map
Before anyone discusses an RECD model, draw the map. A stakeholder map is a list of every party that owns, operates, approves, pays for or is affected by a generator, with a note on what each one controls. It sounds like paperwork, but it is the most useful document in these projects because it shows the gaps before they become disputes.
Common ownership patterns
Most Indian buildings with several equipment owners fall into one or more of these patterns.
| Pattern | Who owns the DG sets | Who operates them | Typical friction point |
|---|---|---|---|
| Landlord-owned, tenant-served | Building owner or landlord | FM company for the landlord | Tenants resist cost pass-through in maintenance charges |
| Tenant-owned sets in a landlord building | Individual tenants (bank, data room, restaurant) | Tenant’s AMC vendor or the FM company | Roof, shaft and chimney rights sit with the landlord |
| FM-operated mixed fleet | Landlord and tenants | One FM company runs all sets | FM has operational control but no spending authority |
| Society or RWA-owned | Residents’ welfare association or society | FM agency or in-house staff | Committee approvals and general body timing |
| Anchor tenant | Anchor (hypermarket, cinema, hospital wing) | Anchor’s own engineering team | Anchor may set its own technical standards |
The pattern decides where authority sits. In a landlord-owned building, the landlord can usually drive the project and recover costs later. Where tenants own sets, the landlord controls the space but not the equipment, and each tenant controls its equipment but not the space. Neither can finish the project alone. For malls, see our guide on RECDs for shopping malls coordinating DG retrofits across tenants.
What each stakeholder controls
For each party on the map, record what equipment they own, what space they control, what they can approve and what they can spend.
| Stakeholder | Owns | Controls space | Can approve | Can spend |
|---|---|---|---|---|
| Landlord | Common sets, chimney, structure | Roof, shafts, DG yard, basement | Structural, roof and shared exhaust changes | Own sets; shared works if the lease allows |
| Tenant | Own DG set | Leased premises | Changes to own set | Own RECD and installation |
| FM company | Usually nothing | Day-to-day access | Work permits, shutdown windows | Usually none without client approval |
| RWA / society | Common sets and areas | Common areas | Via committee or general body | Sinking fund or levy, per bye-laws |
| Consent holder | Varies | Varies | SPCB applications and responses | Varies |
The last row is the one people forget. The consent to operate, or the DG registration, is held by a specific legal entity. That entity, not the FM company and not the RECD supplier, is typically the one the State Pollution Control Board looks to during an inspection. Find out who it is for every set before planning starts. In some buildings the landlord holds one consent listing all sets; in others each tenant registered its own set.
Physical rights: access, shafts and roofs
RECDs take space, add weight and need cable runs for controllers and sensors. In a multi-owner building each of those may need a right that belongs to someone else.
- Roof rights. A roof-mounted RECD needs the landlord or society to permit the location, the structural load and the crane or hoist. See rooftop RECD installation, structural support, lifting and access.
- Shaft rights. Exhaust pipes often rise through a shared shaft. Adding an RECD or a support bracket touches space the tenant does not lease.
- Basement DG rooms. A tenant set may sit in a demised bay, but the corridor, ventilation and lifting route are common areas.
- Cable routes. Controller power and BMS signal cables may cross other tenants’ premises or common trays.
- Working hours. Hot work, crane lifts and noisy fabrication need a work permit, usually from the FM company.
Check leases early. Many older leases say nothing about modifying exhaust systems, which leaves the decision to negotiation. Put the agreed rights in a short access letter or lease side letter before any purchase order is placed.
Shared exhausts and chimneys
The hardest physical issue is a shared chimney. Some buildings connect several sets into one stack to meet chimney height rules. An RECD is normally fitted on each engine’s own exhaust line before it joins the shared section, because each device is sized to one engine’s displacement, exhaust flow and duty. One large device on a common header raises questions about back-pressure interaction between engines, so treat that as a specialist decision. Our post on whether two diesel generators can share one RECD explains why.
Even with one RECD per set, the shared section matters. Each device adds back-pressure to its line, and the combined effect on a shared stack has to be reviewed, especially when sets run together. Measure back-pressure on every line with the other sets running as they would in an outage. The basics are in how exhaust backpressure affects a DG set, and DieselNet is a useful technical reference on diesel exhaust aftertreatment. The owner of the stack, usually the landlord, should hold the drawings and approve every change.
Part 2: The Governance Model
With the map done, design the governance. A governance model answers five questions: who leads, who decides, who pays, who talks to whom, and what happens when people disagree. A two-page project charter signed by every owner is better than a fifty-page agreement nobody reads.
Layer 1: A project lead and a single point of contact
Someone has to drive the project. The natural lead is usually the party that controls the shared space: the landlord or the society. The lead does not need to own every set. Its job is to run the timetable, chair meetings, hold master documents and coordinate suppliers.
Separately, appoint a single point of contact (SPOC), one named person, often a senior FM engineer, who handles day-to-day questions from suppliers, installers and tenants. Suppliers should not get different instructions from four owners. Every technical query goes through the SPOC, who answers it or routes it to the right owner and records the answer. Write down the SPOC’s deputy, what they can decide alone (permit timing, access, minor routing), what they must escalate (cost, scope, anything touching another owner’s equipment) and how quickly owners must respond, for example within three working days.
Layer 2: Decision rights
Not every decision needs every owner.
| Decision type | Examples | Who decides |
|---|---|---|
| Individual | RECD model for a tenant’s set, that tenant’s payment terms | Owner of that set |
| Shared technical | Chimney changes, common supports, roof location, back-pressure limits on a shared stack | Landlord or society, after consulting affected owners |
| Shared commercial | Cost-allocation method, common contractor, testing schedule | All owners, under an agreed consent rule |
“Unanimous” sounds fair but gives any one owner a veto. A common alternative is that the lead proposes, owners have a fixed period to object with reasons, and unresolved objections go to the escalation ladder. In societies, check the bye-laws, because some spending needs a general body resolution.
Layer 3: Who pays for what
Split costs into two buckets.
Set-specific costs belong to that set’s owner: the RECD, controller, set-specific supports, installation on that exhaust line and that set’s testing. For budgeting, see RECD cost in India.
Shared costs benefit more than one owner: structural assessment of the roof or DG yard, shared chimney modifications, crane hire or scaffolding used for several sets, common cable trays and BMS gateways, project coordination, and testing mobilisation booked once for the building.
Shared costs need an allocation method. There are three common bases.
| Method | How it works | Strength | Weakness |
|---|---|---|---|
| By installed kVA | Proportional to rated capacity | Simple, uses undisputed nameplate data | Ignores how much each set runs |
| By run hours | Proportional to recorded hours over a reference period | Reflects actual use | Records may be incomplete; one bad outage year skews it |
| By share of load (kWh) | Proportional to energy generated | Closest to each set’s emission footprint | Needs a reliable energy meter on each set |
A hybrid is often fairest: size-driven works by kVA, use-driven costs by run hours. Use data every owner can check, such as nameplates, hour meters and DG load logs, and fix the reference period in writing so nobody can cherry-pick one later. Also check the lease. Many allow a landlord to recover compliance works through common area maintenance charges; others forbid it. The charter should not contradict the lease without an agreed variation.
Layer 4: Consent holder and compliance records
Every set needs a named consent holder, and the project should keep compliance records in one place even though the equipment has several owners. An inspector usually sees one site, not four businesses. If the landlord’s sets are fully documented and a tenant’s set has nothing, the building as a whole may face questions. Our guide on what happens during a pollution control board inspection explains what is checked.
Keep a shared compliance folder with, for each set: owner, consent holder and reference number; RECD make, model and type-approval certificate (see how to verify a CPCB-tested RECD); commissioning report and test results; maintenance and cleaning records; and the supplier and AMC contacts. Each owner keeps its originals, but copies sit in the shared folder so the SPOC can produce them. For the regulatory background, see the CPCB website and our page on DG set emission regulations.
Layer 5: The communication plan
Multi-owner projects fail quietly when people stop hearing about progress.
| Audience | What they need | Channel and frequency |
|---|---|---|
| All owners | Progress, cost status, decisions due | Written update fortnightly, meeting monthly |
| Tenant operations staff | Shutdown windows, access limits | Email and notice board, 7 days ahead |
| FM and security | Permits, crane movements, hot work | Permit system, daily briefing during works |
| Suppliers and installers | Technical answers, site rules | Through the SPOC only, logged |
| Occupants or residents | Noise, lift use, parking blocks | Circular or notice before each disruptive activity |
Shutdown windows need special care. A tenant with a data room or clinic may not accept its set being out of service in working hours, and may also rely on the landlord’s sets as a second layer of backup. Sequence the work so no owner loses all backup at once; our guide on preserving backup power during an RECD retrofit shows how. In Delhi NCR, plan around GRAP too, because a building with some sets fitted and others not faces awkward choices in winter. See GRAP stage 1 to 4: what changes at each level.
Layer 6: Dispute avoidance
Most disputes are about money, access or blame. You can make them smaller.
- Agree the allocation method before quotes arrive. Once owners see numbers, each prefers the method that suits it.
- Use one technical reference: one drawing set, one back-pressure limit per set, one testing protocol.
- Record every scope change with a note on who pays. See managing scope changes after an RECD order.
- Separate snagging by owner, so one party’s open item does not hold up another’s handover.
- Set an escalation ladder with time limits: SPOC, then owners’ representatives, then senior management, then an independent technical expert for technical issues.
- Keep numbered minutes, circulated within two days. Disputes often start with “we never agreed that”.
Worked Example: A Mixed-Use Building in Noida (Illustrative)
The figures below are illustrative only. They show the method, not real prices or a real building.
The building
A ten-storey mixed-use building has retail below and offices above.
| Set | Owner | Rating | Location | Serves |
|---|---|---|---|---|
| DG-1 | Landlord | 750 kVA | Roof | Common areas, lifts, shared tenant backup |
| DG-2 | Landlord | 750 kVA | Roof | Common areas, lifts, shared tenant backup |
| DG-3 | Tenant A (bank branch and data room) | 250 kVA | Basement bay | Tenant A only |
| DG-4 | Tenant B (anchor restaurant group) | 500 kVA | Rear yard | Tenant B only |
Total installed capacity is 750 + 750 + 250 + 500 = 2,250 kVA. DG-1 and DG-2 share a roof chimney. DG-3 exhausts through a shaft rising past other tenants’ floors. DG-4 has its own short stack. The FM company operates DG-1 and DG-2, issues permits for the building and acts as SPOC. The landlord holds the consent for its two sets; each tenant holds its own registration.
The shared cost pool
Each owner buys and installs its own RECD. The shared pool is:
| Shared item | Illustrative cost (₹) |
|---|---|
| Structural assessment of roof and shaft supports | 1,50,000 |
| Chimney and shaft modifications, support brackets | 6,00,000 |
| Crane hire and roof access works (one mobilisation) | 2,50,000 |
| Project coordination and SPOC time | 1,20,000 |
| Coordinated testing mobilisation | 80,000 |
| Total | 12,00,000 |
Check: 1,50,000 + 6,00,000 + 2,50,000 + 1,20,000 + 80,000 = 12,00,000.
Reference data (last 12 months, illustrative)
| Owner | Installed kVA | Run hours | Energy generated (kWh) |
|---|---|---|---|
| Landlord (DG-1 + DG-2) | 1,500 | 400 | 2,02,500 |
| Tenant A (DG-3) | 250 | 150 | 22,500 |
| Tenant B (DG-4) | 500 | 250 | 75,000 |
| Total | 2,250 | 800 | 3,00,000 |
Landlord hours are the two sets combined. A sense check on the energy column: Tenant A’s 22,500 kWh over 150 hours averages 150 kW, about 75% of a 250 kVA set’s 200 kW at 0.8 power factor. Tenant B’s 75,000 kWh over 250 hours is 300 kW, also 75% of 400 kW. The landlord’s 2,02,500 kWh over 400 set-hours is about 506 kW per running hour.
Allocation under each method
| Owner | kVA share | By kVA (₹) | Hours share | By hours (₹) | kWh share | By kWh (₹) |
|---|---|---|---|---|---|---|
| Landlord | 66.67% | 8,00,000 | 50.00% | 6,00,000 | 67.50% | 8,10,000 |
| Tenant A | 11.11% | 1,33,333 | 18.75% | 2,25,000 | 7.50% | 90,000 |
| Tenant B | 22.22% | 2,66,667 | 31.25% | 3,75,000 | 25.00% | 3,00,000 |
| Total | 100% | 12,00,000 | 100% | 12,00,000 | 100% | 12,00,000 |
The working:
- kVA: 1,500 ÷ 2,250 = 2/3, so ₹8,00,000. 250 ÷ 2,250 = 1/9, so ₹1,33,333. 500 ÷ 2,250 = 2/9, so ₹2,66,667.
- Run hours: 400 ÷ 800 = 50%, so ₹6,00,000. 150 ÷ 800 = 18.75%, so ₹2,25,000. 250 ÷ 800 = 31.25%, so ₹3,75,000.
- kWh: 2,02,500 ÷ 3,00,000 = 67.5%, so ₹8,10,000. 22,500 ÷ 3,00,000 = 7.5%, so ₹90,000. 75,000 ÷ 3,00,000 = 25%, so ₹3,00,000.
Each column totals ₹12,00,000.
What the numbers show
Tenant A’s bill ranges from ₹90,000 to ₹2,25,000, a factor of 2.5. Its set is small but runs a relatively high number of hours for its size, so run hours penalise it, while its modest energy output means kWh favours it. The landlord pays least under run hours because its two large sets run relatively few hours for their combined capacity. This is exactly why the method must be agreed before anyone sees the figures.
The agreed hybrid
The owners agree that size-driven works should follow kVA and use-driven costs should follow run hours. To keep it simple, they split the whole pool 50% by kVA and 50% by run hours.
| Owner | Half of kVA allocation (₹) | Half of hours allocation (₹) | Hybrid total (₹) |
|---|---|---|---|
| Landlord | 4,00,000 | 3,00,000 | 7,00,000 |
| Tenant A | 66,667 | 1,12,500 | 1,79,167 |
| Tenant B | 1,33,333 | 1,87,500 | 3,20,833 |
| Total | 6,00,000 | 6,00,000 | 12,00,000 |
Check: 7,00,000 + 1,79,167 + 3,20,833 = 12,00,000.
Tenant A then points out that part of the shaft work serves only DG-3. That is a fair challenge. If ₹1,00,000 of the chimney and shaft line relates only to DG-3, it should move to Tenant A as a set-specific cost and the shared pool should drop to ₹11,00,000 before allocation. Splitting line items honestly does more for trust than any formula.
How it ran
The landlord led, and the FM chief engineer was SPOC. All owners signed a two-page charter covering the cost method, decision rights, escalation ladder and shared compliance folder. DG-1 and DG-2 were fitted one at a time so landlord backup was never fully lost. DG-3 was fitted on a Sunday with the landlord’s sets confirmed available. One crane booking served both roof devices and DG-4’s yard device, which is why crane hire sat in the shared pool. Back-pressure was recorded on every line, with the other sets running, against one agreed limit per set.
Frequently Asked Questions
If the landlord fits RECDs but a tenant refuses, who is responsible?
Typically, each consent or registration holder is responsible for its own set. A landlord cannot usually force a tenant to buy equipment unless the lease allows it, though it may rely on lease clauses requiring tenants to follow applicable law, or control access for works on its roof and shafts. Check the lease and take legal advice if the tenant will not move.
Can one supplier handle every set in the building?
Yes, and it often simplifies coordination, testing and spares. Each owner must still agree to it, and each RECD must be sized to its own engine. One supplier does not mean one model. See choosing CPCB-approved RECD vendors.
What if run-hour records are missing for one set?
Agree a fallback in the charter: use kVA for that set, or an estimate all owners accept. Do not let one missing record block the whole allocation.
Does the FM company carry compliance responsibility?
The FM company is responsible for what its contract says, such as daily checks and records. Legal responsibility under the consent typically stays with the consent holder. Our companion post on who owns RECD performance when generator operation is outsourced explains the split.
What if a set changes owner mid-project?
Treat it as a scope change. Update the map, transfer documents, confirm the new owner accepts the agreed allocation, and check whether the consent or registration needs updating.
Talk to Aceget About Your Building
Aceget supplies CPCB type-approved Retrofit Emission Control Devices for DG sets from 25 kVA to 2500 kVA. If your building has several equipment owners, our team can review each set’s details so devices are sized individually while the project runs on one plan. Review our certifications or contact our team to discuss your site.
Related Reading
- Who Owns RECD Performance When Generator Operation Is Outsourced?
- Planning RECD Fitment Across DG Sets of Different Makes and Ages
- Scheduling RECD Work Around a Factory’s Annual Shutdown
- RECDs for Shopping Malls: Coordinating DG Retrofits Across Tenants
- Customer and Installer Responsibilities in an RECD Project