RECD Planning for Generators Relocated Between Project Sites

Construction contractors, infrastructure developers and EPC firms move diesel generators all the time. A 320 kVA set that powered a metro station box in Gurugram for eighteen months may next run a tunnel ventilation fan in Uttarakhand or a batching plant near a port in Gujarat. The generator is treated as portable; the retrofit emission control device (RECD) on its exhaust often is not, and that is where problems start.

An RECD is selected for a specific engine, a specific exhaust arrangement and a specific duty. When a set moves, some of those inputs stay the same and some change completely. A relocated generator can arrive at its new site with an RECD that is still perfectly suitable, one that needs minor rework, or one that should really stay behind. Working out which applies, before the crane arrives, saves time, money and an awkward conversation with the new site’s pollution control board.

Relocation is risky for three reasons: the device’s design inputs (duty, exhaust routing, ambient conditions) may change, road transport and rigging stress ceramic substrates and sensor joints, and consent and test history do not move by themselves. This guide, for project managers, plant heads, EHS leads and DG maintainers, compares what changes when a set moves, then gives a relocation procedure, a worked example and a handover checklist. For the wider picture, see RECDs for construction projects with changing power demand.

What changes when the set moves

For each factor, ask whether the new site differs and what that means for the RECD.

FactorWhat can change at the new siteWhy it matters for the RECDWhat to do before the move
Duty and loadPrime power instead of standby, longer runs, lower average load, more start-stop cyclesLow load and short runs reduce exhaust temperature, so passive regeneration may not happen; heavier duty loads the filter fasterGet the new site’s expected load profile and run hours; compare with the original sizing basis
Exhaust height and directionNew stack height, different discharge direction, new routing around site cabins or hoardingsExtra pipe length and bends add back-pressure; a new outlet may face workers or neighboursAsk for a site layout sketch; estimate new pipe length and bend count; check against the engine’s back-pressure limit
Neighbours and air intakesHousing, schools, hospitals, office HVAC intakes or site welfare cabins nearbyEven filtered exhaust carries heat, gases and odour; regeneration events can be noticeableMark sensitive receptors and fresh air intakes on the layout; agree outlet orientation
AltitudeHill sites at 1,500 m or moreThinner air changes combustion, exhaust temperature and flow; engine derating may alter load shareCheck engine derating and whether the RECD’s sizing still holds
DustQuarry, tunnelling, earthworks, cement or aggregate handlingDust affects engine air filters first, but poor intake filtration increases soot and ash loadingPlan for more frequent air filter checks and closer back-pressure monitoring
Coastal airPort, shipyard, coastal highway or desalination siteSalt-laden air attacks fasteners, sensor connectors, cable glands and external surfacesInspect coatings, upgrade fasteners and connectors where needed, add a corrosion check to the service plan
State rules and consentA different state pollution control board, different consent conditions, different registration processWhat was accepted in one state may need fresh documentation or approval in anotherContact the new SPCB or your environmental consultant early; collect type approval and test documents
GRAP and air quality controlsMoving into or out of Delhi NCR, or into another area with seasonal restrictionsDG use rules during GRAP stages can depend on emission control status and fuel typeConfirm the rules that apply at the new location and season
Power supply for the controllerDifferent site distribution, no permanent auxiliary supply at firstIf the RECD controller or heater needs auxiliary power, a new supply point must be arrangedList auxiliary power needs and include them in the temporary electrical design
Who operates the setA new site team, a local AMC contractor or a rental operatorOperators who do not know the RECD may ignore alarms or skip checksPlan a handover briefing and operator training at the new site

Not every row will change for every move. A set moving between two Noida tower sites may change only its exhaust routing and neighbours. A set moving from Delhi to Shimla changes almost everything. What usually stays the same is the engine itself and the RECD’s type approval, so if the engine has not been overhauled or modified, the basic engine-to-device match still holds. The question is whether the new installation and operating conditions still sit inside the conditions that match was based on.

Does the RECD move with the set or stay behind?

Make this decision deliberately, not by default. There are three realistic options:

OptionWhen it fitsWatch out for
A: RECD moves with the setSame engine, similar duty, layout can keep back-pressure in limitsThe most common choice; history stays with the set
B: RECD stays behind on a replacement setDeparting site still needs power and the exhaust arrangement is provenAn RECD is matched to an engine; read can an RECD be transferred to another diesel generator
C: RECD replaced or reconfiguredDuty changes sharply, such as standby to 20-hour prime use at a hill siteForcing an unsuitable device into a new duty leads to blocked filters

A simple decision rule

Ask the following four questions. If all four answers are “yes”, Option A is usually fine. If any answer is “no”, involve the RECD supplier before finalising the plan.

  1. Is the engine unchanged since the RECD was commissioned?
  2. Will the new duty and load profile fall within the original sizing basis?
  3. Can the new exhaust layout keep back-pressure within the engine maker’s limit?
  4. Are the new site’s ambient conditions (altitude, dust, salt) covered by the original selection?

The relocation procedure

The procedure below follows a set from the last day at the old site to normal operation at the new one. Adapt it into your method statement and attach it to the work permit.

Phase 1: Pre-move assessment (two to four weeks before)

  1. Collect the new site data. Expected load profile, run hours per day, layout sketch, stack height requirement, location of neighbours and intakes, altitude, ambient conditions and the name of the SPCB.
  2. Pull the RECD’s history. Commissioning report, test reports, back-pressure trend, cleaning and service records, alarm history and any warranty correspondence.
  3. Record the current condition. Take a back-pressure reading at a known load before shutdown, photograph the device, its supports and sensor connections, and note any alarms.
  4. Run the four-question decision rule. Decide between options A, B and C, and get the supplier’s view where needed.
  5. Check consent and registration. Start the conversation with the new state board or your consultant. Our guide on getting a pollution NOC for a DG set is a useful starting point.
  6. Design the new exhaust layout. Estimate pipe lengths, bends, supports and the outlet position. Plan for thermal expansion and include flexible connections where needed.

Phase 2: Pre-shutdown checks at the old site

  • If the RECD needs active or assisted regeneration, consider a regeneration cycle (or a period of high load) before the final shutdown so the filter travels in a cleaner state. Follow the supplier’s guidance; DieselNet’s overview of filter regeneration explains the background.
  • Read and export the controller’s event log and settings.
  • Let the exhaust cool fully before anyone touches it.

Phase 3: Dismantling

  1. Isolate the set electrically and mechanically under your permit-to-work system.
  2. Disconnect and label every sensor, cable and controller connection. Photograph each one before removal.
  3. Cap open exhaust ends and sensor ports to keep out dust, water and insects.
  4. Remove the RECD as a unit where possible. Use the supplier’s lifting points, not the sensor bosses or pipe flanges.
  5. Keep gaskets, fasteners and clamps in labelled bags. Plan to replace gaskets on reinstallation rather than reuse them.
  6. Check the device for visible damage before it leaves site, so damage in transit can be identified later.

Phase 4: Transport

  • Transport the RECD in an orientation the supplier accepts, on a padded cradle, strapped so it cannot shift, with nothing stacked on it.
  • If the RECD stays on the generator canopy or skid during transport, check that its supports are designed for road loads, not just static weight. The post on RECD fitment on trailer-mounted generators goes into bracing in detail.
  • Move the controller and loose sensors in a separate, padded box, kept dry.

Phase 5: Reinstallation at the new site

  1. Confirm the foundation or plinth, the canopy position and the exhaust route match the approved layout.
  2. Fit the RECD on supports designed for the new layout. Do not let the device hang from the engine’s exhaust manifold or turbocharger outlet.
  3. Fit new gaskets and check flange alignment. Misalignment forced together with bolts is a common source of leaks and cracked joints.
  4. Fit flexible bellows where the design calls for them, at the correct pre-set length.
  5. Route sensor cables away from hot surfaces and secure them properly.
  6. Connect the controller to its auxiliary supply and confirm it powers up without fault codes.
  7. Restore any links to the site’s monitoring system or remote alerts.

Phase 6: Post-move checks and recommissioning

Run the set under a controlled load and record:

  • Back-pressure at idle and at one or two load points, compared with the pre-move reading at the same kW load.
  • Exhaust temperature upstream of the RECD.
  • Leaks at all joints (visual and, when safe, by careful checking for soot marks after a run).
  • Sensor readings that make sense against each other.
  • Controller status, alarms and event log entries.
  • Visible smoke at the outlet during start-up and load steps.

Compare like with like. A back-pressure reading at 60% load is not comparable with one at 30% load. Our post on comparing RECD pressure readings at different generator loads explains how to make fair comparisons.

Retest triggers after a move

Not every relocation needs a fresh emissions test. Treat this table as a planning aid and confirm requirements with your SPCB and supplier.

Situation after the moveRetest likely needed?Reason
Same engine, same duty, similar layout, back-pressure matches pre-move readingUsually not, but keep the comparison recordConditions have not materially changed
New exhaust layout with significantly higher back-pressureReview with supplier; possiblyChanged operating conditions could affect performance and the engine
New state board requests evidence of performanceYes, if askedConsent conditions take priority
Device found damaged or substrate suspected crackedYes, after repair or replacementDamage may allow particulate to bypass the filter
Engine overhauled or modified before reinstallationYesThe engine side of the match has changed
RECD moved to a different setYesThe device is now on a different engine
Large shift in duty, such as standby to continuous primeReview with supplier; likelySoot loading and regeneration behaviour change

For more detail, read when to retest an RECD after DG set changes.

Worked example (illustrative): a 320 kVA set leaving a metro site

The numbers below are illustrative. They show the reasoning, not a real project or a guaranteed result.

The starting point

A contractor runs a 320 kVA DG set at an elevated metro station site in Delhi NCR. The set has an RECD fitted and commissioned about 16 months ago. At the metro site it ran mainly as backup for site lighting, cranes and a batching plant during grid outages, averaging about four hours a day at 45–60% load.

The pre-move record at a steady 180 kW load shows back-pressure within the engine maker’s limit, with a comfortable margin. The exhaust run is short: about 3 metres of pipe and two bends, discharging vertically at 3 metres above the canopy.

The set is now moving to one of two possible sites.

Scenario 1: a hill road project at about 1,900 m

The new site is a road widening and tunnel portal project in a hill state. The set will power tunnel ventilation fans and site lighting, running 16–18 hours a day.

What changes:

  • Duty: from about four hours a day of backup use to 16–18 hours of near-continuous prime use. Average load is expected to be around 55% of the derated output.
  • Altitude: the engine maker’s derating means the set will deliver less than its sea-level rating. The site team must confirm actual available kW and that the fan loads fit within it.
  • Exhaust layout: the set sits in a cutting below the road, close to a site office. To clear the office and discharge above the cutting edge, the exhaust needs about 9 metres of pipe and four bends.
  • Dust: blasting and excavation create heavy dust. Air filter servicing will need to be more frequent.
  • Neighbours: a site office and a labour camp are within 40 metres.

The assessment:

CheckFindingAction
Engine unchanged?YesNo action
Duty within sizing basis?Unclear: much longer running, though at moderate loadSupplier review of the new profile
Back-pressure within limit?Pre-move margin was comfortable; the longer run adds pressure dropPipe sizing calculation; possibly increase pipe diameter on the extended section
Ambient covered?Altitude and dust not part of the original selection discussionSupplier review; read the high-altitude and dusty location guides

Longer, steadier running at moderate load may actually help regeneration by keeping exhaust temperatures up, so the duty change is not necessarily bad news. But altitude, dust and the longer exhaust run all need checking. The contractor’s plan: supplier review, revised exhaust design with a larger-bore extension, new supports, more frequent back-pressure logging in the first month and a documented comparison against the pre-move reading. Relevant reading: RECD selection for high-altitude diesel generators and RECDs in dusty industrial locations.

Scenario 2: a coastal port expansion

The alternative site is a berth expansion project about 300 metres from the sea. The set will act as backup for a site office and workshop, running perhaps two hours a day at 25–35% load.

The exhaust run is similar and short, so pipework back-pressure should be close to the old site, but a different state board is involved. The real concerns are regeneration under light load (cooler exhaust, more soot between regeneration opportunities) and corrosion of fasteners, connectors and uncoated steel. Options include arranging periodic higher-load running (for example, a scheduled load-bank session, if the site can arrange one), checking whether the RECD’s regeneration strategy suits the new duty, and upgrading external hardware. The guides on choosing an RECD for generators running at low load and RECDs in coastal salt-laden environments cover both concerns.

What the example shows

The same set, with the same RECD, faces quite different risks depending on where it goes. A blanket rule such as “the RECD always moves with the set, no questions asked” would have missed the back-pressure issue at the hill site and the regeneration issue at the port. A blanket rule such as “always re-specify” would waste money on Scenario 2, where a few operating changes and hardware upgrades may be enough.

Document continuity: the RECD travels with its history

An RECD without records is a device you cannot easily defend. When a set moves, its documents must move with it, and they must clearly tie the device to the engine.

The relocation file

Create a relocation file for each move. Keep it with the set’s master records and give a copy to the new site. It should include:

  • Engine, generator and RECD identification: models, serial numbers, nameplate photographs and type approval documents.
  • The original commissioning report and any emissions test reports.
  • The pre-move condition record, dismantling, transport and reinstallation records.
  • Post-move check results compared with pre-move results, and any supplier recommendation.
  • Consent, registration and correspondence with the new state board.

Keep identification and logs continuous

Keep the RECD’s serial plate intact and readable; if it is damaged in the move, tell the supplier at once. Inspectors check that the device on the exhaust is the one in the documents. Our guide on verifying a CPCB-tested RECD shows what inspectors typically look for, and the CPCB website is the authoritative source for current notifications.

After the move, check the controller clock so new log entries line up with the exported old ones. A noted gap (“in transit, 3–6 March”) is fine; a log that restarts at a default date looks careless.

Timing moves around GRAP

GRAP restrictions on DG use in Delhi NCR tighten as winter air quality worsens, typically from October onwards. A set arriving at an NCR site in November with incomplete papers or a faulty RECD can sit idle while the project waits for power. Plan NCR arrivals before the season where you can, have the RECD documents at the new site on day one and check the current stage before commissioning (see GRAP rules for DG sets in Delhi NCR). When a set leaves NCR, do not assume NCR rules, or their absence, apply in the new state.

Project handover checklist

Use this checklist when the set is handed from the dispatching site to the receiving site. Both site leads should sign it.

Dispatching site

  • Pre-move back-pressure reading recorded at a stated kW load
  • Photographs of the RECD, supports, sensors and controller taken
  • Controller event log and settings exported
  • Open alarms recorded and explained
  • Connections labelled and ports capped
  • Relocation file updated and copied to the receiving site
  • Spare gaskets, sensors and consumables listed and packed

Receiving site

  • Exhaust layout approved, with back-pressure estimate
  • Outlet position reviewed for neighbours and fresh air intakes
  • Auxiliary supply for the controller available
  • Consent and registration status confirmed with the SPCB or consultant
  • New gaskets fitted, flanges aligned, bellows set correctly
  • Post-move checks complete and compared with pre-move readings
  • Retest need assessed using the trigger table
  • Operators briefed on RECD checks and alarms
  • Service schedule adjusted for new duty and ambient conditions

Sign-off

RoleNameDateSignature
Dispatching site lead
Receiving site lead
DG maintainer
EHS representative

Frequently asked questions

Can we move a set with its RECD without telling the supplier?

You can physically move it, but it is wise to inform the supplier, especially if the duty, layout or ambient conditions change. Warranty terms may also require notice or approved installation practice. Check your RECD warranty terms before the move.

Does a relocated set need a fresh emissions test?

Not always. If the engine, duty and layout are essentially unchanged and post-move checks match the pre-move baseline, a test may not be needed. A changed engine, a different set, damage, a big duty change or a request from the new state board are all good reasons to retest.

What if the new site has no permanent power for the RECD controller?

Plan a temporary auxiliary supply as part of the site’s electrical design. Ask the supplier for the actual requirement and see RECD controller and heater power supply requirements.

Who is responsible for compliance at the new site?

Typically the owner or occupier named in the new site’s consent. On project sites this may be the principal contractor, the developer or a subcontractor. Check the contract and consent documents, and make sure everyone knows who holds the obligation.

Plan the move before the crane arrives

Aceget supplies CPCB type-approved Retrofit Emission Control Devices for DG sets from 25 kVA to 2500 kVA. If you are planning to relocate generators between project sites, share the new site’s duty, layout and conditions with us early. You can review our certifications or contact our team to discuss your next move.

Related Reading



2 Comments

Leave a Reply