How to Rank DG Sets for a Phased RECD Rollout

Few organisations can retrofit every DG set at once. Budgets come in tranches, installation crews are limited, and some sets can only be taken out of service during an annual shutdown. So the real question is not “should we fit RECDs?” but “which sets go first, and why?”

Most teams answer informally: the biggest set first, or the one the inspector mentioned. That works until someone asks you to justify the order, or the budget is cut halfway.

A weighted scoring model turns that debate into a table and records the reasoning. This post builds one for a phased RECD rollout, scores eight illustrative DG sets, and shows how to handle ties, constraints and re-ranking.

Why a Scoring Model Beats Intuition

A scoring model does three things a gut-feel list cannot:

  1. It makes trade-offs visible. A 1,500 kVA standby set that rarely runs and a 250 kVA set beside a fresh-air intake both have a case. The model shows exactly how much each criterion contributes.
  2. It survives scrutiny. When finance, EHS or an auditor asks why Set C went before Set B, you can show the scores, not a recollection of a meeting.
  3. It re-ranks cheaply. Update one cell and the order updates itself.

The model is a decision aid, not a decision maker. Build it with the people who know the sets: the facility manager, EHS lead, DG maintainer and budget holder. A result that looks wrong usually means a criterion or weight is missing.

Step 1: Choose the Criteria

Nine criteria cover most sites. Think hard before removing regulatory, run hours or exposure, as these carry most of the compliance and environmental logic.

Regulatory deadline and state notifications

What does your compliance register say about each set’s location? Delhi NCR sets face GRAP restrictions and specific RECD requirements, while other states follow their own SPCB timelines. A set at a site with an imminent compliance date should rank higher than an identical set at a site with no current requirement. For background, see DG set emission regulations, the state-wise comparison of pollution control norms and the GRAP rules for DG sets in Delhi NCR. The CPCB website is the primary source for central notifications.

Run hours

A set that runs 1,100 hours a year emits far more particulate matter than one that runs 60 hours for monthly tests, so fitting the RECD on the busy set first avoids more PM per rupee. Use real data from hour meters or DG load logs, not estimates. DieselNet is a good technical reference on how diesel PM forms and is controlled.

Rating and kVA band

Larger engines produce more PM per running hour, and some notifications treat kVA bands differently. Keep the weight moderate: a big set that hardly runs may matter less than a mid-sized set that runs daily.

Location and exposure

Where does the exhaust go? A stack near a residential boundary or beside an air-handling unit’s fresh-air intake creates direct exposure; a set in an open yard creates much less. Exposure also drives complaints, and complaints drive inspections.

Engine age and CPCB stage

Older engines built to earlier norms generally emit more PM than newer ones. Score older and earlier-stage engines higher. If you need a refresher on the stages, see CPCB II vs CPCB III vs CPCB IV+ norms explained.

Condition

This one runs the other way. A healthy engine is a good RECD candidate. A set with heavy smoke, oil consumption or blow-by needs attention before any after-treatment is fitted, because those problems load the filter quickly. Score good condition higher, and treat very poor condition as a gate (more on that below). See whether to complete an engine overhaul before fitting an RECD.

Criticality and downtime availability

A guard-house set can be isolated on any weekday; a production-line set may only be free during the annual shutdown. Score easy downtime higher, because sets you can reach are the ones you can finish in the phase.

Ease of installation

Ground-floor sets with straight exhaust runs are quicker and cheaper than basement or rooftop sets needing cranes, structural checks or long ducting.

Budget fit

Can the current budget tranche cover this set without separate approval? For cost drivers, see RECD cost in India.

Step 2: Write a Scoring Rubric

Each criterion is scored from 1 to 5, where 5 means a stronger case to retrofit early. A rubric stops people scoring the same set differently. The rubric below is illustrative; adjust the bands to your own portfolio.

Criterion135
Regulatory deadlineNo current or foreseen requirementRequirement expected, no dateCovered now, deadline in current window
Run hours (per year)Under 100300–600Over 1,000
Rating (kVA)Under 100200–499750 and above
ExposureRemote, open yardWithin site, moderate occupancy nearbyNear residences or air intakes
Engine age and stageNewest, latest stageMid-lifeOldest, earliest stage
ConditionNeeds overhaul firstServiceable, minor issuesExcellent, clean history
Downtime availabilityOnly in annual shutdownPlanned weekends possibleCan isolate any working day
Ease of installationBasement or roof, crane, long ductingSome fabrication, moderate accessGround level, short straight run
Budget fitNeeds separate approvalFits with some reallocationFits easily in current tranche

Scores of 2 and 4 sit between the anchors. For run hours, for example, 100–300 hours scores 2 and 600–1,000 scores 4. For rating, 100–199 kVA scores 2 and 500–749 kVA scores 4.

Step 3: Assign Weights

Weights express what matters most to your organisation. They must add up to 100. This illustrative set gives most of the weight to compliance and environmental benefit, with practical factors acting as modifiers.

CriterionWeightReasoning
Regulatory deadline20Missing a deadline risks sealing and penalties
Run hours15Main driver of PM actually avoided
Exposure15Health impact and complaint risk
Rating10Bigger engines, more PM per hour
Engine age and stage10Older engines emit more
Condition10Healthy engines give reliable results
Downtime availability10Determines whether the set can be done in the phase
Ease of installation5Affects time and cost, rarely decisive
Budget fit5Tie-breaker within a tranche
Total100

The formula for each set is:

Weighted score = (sum of each criterion score × its weight) ÷ 5

Dividing by 5 converts the result into a score out of 100. A set scoring 5 on everything gets 100; a set scoring 1 on everything gets 20.

Step 4: Score the Sets (Illustrative Worked Example)

Here is an illustrative manufacturing company with eight DG sets: seven at a plant in Delhi NCR and one at a second site in Gujarat. All figures are invented for illustration.

SetRatingRole and locationRun hours/yrYearNotes
A1,010 kVAMain plant supply, 30 m from residential boundary1,1002013Good condition, only available in shutdowns
B500 kVAAdmin block, ground level4502015Good condition
C250 kVACanteen block, beside AHU fresh-air intake4202016Serviceable
D750 kVAProcess sync pair, lead set7002013Good condition
E750 kVAProcess sync pair, lag set, nearer boundary5002013Good condition
F125 kVASewage treatment plant2002019Serviceable
G62.5 kVAGate house802011Visible smoke on start, oil top-ups rising
H1,500 kVAGujarat site standby, no current notification602018Excellent

The raw scores

SetReg (20)Run (15)Exp (15)Rating (10)Age (10)Cond (10)Downtime (10)Ease (5)Budget (5)
A555544232
B533434444
C535333545
D543544333
E534544333
F422223555
G411142555
H212535221

A few scoring notes. F and G are covered by the NCR requirement, but the site’s compliance register shows a later date for them, so they score 4 on regulatory rather than 5. H scores 2 because the Gujarat site has no current requirement, but the company expects one. G is old (score 4 on age) but in poor condition (score 2).

Calculating one set in full: Set A

CriterionScoreWeightScore × weight
Regulatory520100
Run hours51575
Exposure51575
Rating51050
Age and stage41040
Condition41040
Downtime21020
Ease3515
Budget2510
Sum425

Weighted score = 425 ÷ 5 = 85.0.

Calculating one more: Set C

100 (Reg 5 × 20) + 45 (Run 3 × 15) + 75 (Exp 5 × 15) + 30 (Rating 3 × 10) + 30 (Age 3 × 10) + 30 (Cond 3 × 10) + 50 (Downtime 5 × 10) + 20 (Ease 4 × 5) + 25 (Budget 5 × 5) = 405. Weighted score = 405 ÷ 5 = 81.0.

Notice how Set C, only a quarter of Set A’s rating, comes second. Its exposure beside an air intake and its easy downtime outweigh its moderate run hours and size. That is exactly the kind of result a scoring model surfaces and intuition tends to miss.

The full ranked table

RankSetSum of score × weightWeighted score (÷ 5)
1A42585.0
2C40581.0
3=D39579.0
3=E39579.0
5B38076.0
6F31062.0
7G28056.0
8H25050.0

For checking, the other sums are: B = 100 + 45 + 45 + 40 + 30 + 40 + 40 + 20 + 20 = 380. D = 100 + 60 + 45 + 50 + 40 + 40 + 30 + 15 + 15 = 395. E = 100 + 45 + 60 + 50 + 40 + 40 + 30 + 15 + 15 = 395. F = 80 + 30 + 30 + 20 + 20 + 30 + 50 + 25 + 25 = 310. G = 80 + 15 + 15 + 10 + 40 + 20 + 50 + 25 + 25 = 280. H = 40 + 15 + 30 + 50 + 30 + 50 + 20 + 10 + 5 = 250.

Step 5: Break Ties With a Written Rule

D and E tie at 79.0. They are twin 750 kVA sets with the same age and condition, but different profiles. D runs more (it is the lead set), while E sits nearer the boundary. Their run-hours and exposure contributions swap exactly, because both criteria carry a weight of 15.

Agree a tie-break order before you score, so nobody can choose a rule to suit a favourite set. A sensible order is:

  1. Higher regulatory score.
  2. Higher exposure score.
  3. Higher run hours score.
  4. Higher downtime availability score.

D and E both score 5 on regulatory, so rule 2 decides: E (exposure 4) goes ahead of D (exposure 3). Some teams prefer run hours ahead of exposure. Either is defensible, as long as it is written down first.

There is a second point here. In a lead-lag pair, the lead and lag roles can be rotated. If E is retrofitted first, the site might make E the lead set afterwards to put more running hours through a set that already has an RECD. That interacts with soot loading and regeneration, so read how lead-lag rotation affects RECD operating conditions before you change the rotation.

Step 6: Apply Gates and Hard Constraints

A score ranks sets. It does not schedule them. Before turning the ranking into phases, apply two kinds of filter.

Gates: sets that should not proceed yet

A gate is a condition that pauses a set regardless of its score. Common gates are:

  • Condition score of 1: overhaul or repair first, then re-score.
  • Condition score of 2: inspect before ordering. Set G falls here. Visible smoke on start and rising oil top-ups suggest a problem that would load a filter quickly.
  • Unknown exhaust layout: no order until a site survey confirms the fit.
  • Planned replacement: if a set will be replaced within a year or two, compare the retrofit with buying a new set. See retrofitting an old DG set with an RECD: is it worth it?

Constraints: sets that cannot be done together or whenever

  • Redundancy pairs. D and E back each other up on the process line. Only one can be out at a time, and the second waits until the first is returned and tested. The method for this is in sequencing RECD installations on an N+1 generator system.
  • Shutdown windows. Set A can only be isolated during the plant’s planned maintenance shutdown, so its slot is fixed by the production calendar.
  • Budget tranches. In this illustrative case, the Phase 1 budget covers three devices.
  • Seasons, crews and lead times. In NCR, avoid outage-heavy summer weeks and plan testing around GRAP stages. Fabrication and delivery times may cap how many sets a quarter can absorb.

Step 7: Turn the Ranking Into Phases

Applying the tie-break, gates and constraints to the ranked list gives this illustrative plan.

PhaseSetsReasoning
Phase 1A, C, ETop three after tie-break. A is fitted during the planned shutdown; C and E are scheduled around it. E goes before D.
Phase 2D, BD follows only after E is returned and tested. B is next in rank.
Phase 3F, G, HF proceeds. G proceeds only if inspection clears it. H is ordered when the Gujarat requirement is confirmed or bundled with a site visit.

Constraints sometimes force a lower-ranked set ahead, for example when a higher-ranked set’s shutdown is months away and a crew is idle. That is acceptable if the reason is recorded.

When you present the plan, attach the scoring table to your internal approval note for the RECD purchase. It answers most “why this set first?” questions before they are asked.

Step 8: Test the Ranking for Sensitivity

Weights are judgements, so check whether a reasonable change would alter your Phase 1 list.

In this illustrative test, the team raises exposure from 15 to 25 and removes ease and budget (5 each) altogether. The total is still 100.

SetOriginal scoreSensitivity scoreChange in rank
A85.090.0Stays 1st
C81.082.0Stays 2nd
E79.081.0Now clearly 3rd, no tie
D79.079.04th
B76.074.0Stays 5th
F62.056.0Stays 6th
H50.051.0Rises to 7th
G56.048.0Falls to 8th

To check one: Set E under the new weights is 100 + 45 + (4 × 25 = 100) + 50 + 40 + 40 + 30 = 405, and 405 ÷ 5 = 81.0. Set G is 80 + 15 + (1 × 25 = 25) + 10 + 40 + 20 + 50 = 240, and 240 ÷ 5 = 48.0.

The Phase 1 sets (A, C, E) do not change, the D and E tie resolves the same way as the written tie-break, and only the bottom two swap. The plan does not hang on one contested weight.

Step 9: Re-Rank When the Facts Change

A ranking is a snapshot. Re-run it at the end of each phase, and also whenever one of these triggers occurs:

  • A new central or state notification, or a change in the GRAP pattern for your area.
  • A meaningful change in a set’s run hours or load, for example a new building or production line.
  • A set failing, being overhauled or being scheduled for replacement.
  • A complaint, inspection or budget change.
  • Lessons from completed installations, such as harder access than expected.

Illustrative re-rank

Six months into the rollout, the admin block gains a server room. Set B’s annual run hours jump from 450 to 1,050 because it now runs through more grid outages at higher load. Its run hours score rises from 3 to 5.

New sum for B = 380 + (5 − 3) × 15 = 380 + 30 = 410. Weighted score = 410 ÷ 5 = 82.0.

B now outranks D (79.0), so if D has not started, B moves ahead of it in Phase 2. If the server room also makes B harder to take out, re-score downtime availability too.

Practical Tips for Building the Model

  • Keep it in one shared spreadsheet, with scores, weights and formulas visible. Lock the weights once agreed.
  • Record the evidence behind each score, such as the hour-meter reading, the distance to the boundary or the survey note.
  • Score missing data as 3 and flag it, then replace it with real data before the phase is finalised.
  • Do not let one criterion carry more than about a quarter of the weight, or the model becomes a single-factor list in disguise.

FAQ

How many criteria should a phased RECD rollout model use?

Between six and ten works for most organisations. Fewer than six tends to miss practical constraints; more than ten makes scoring slow and weights too thin to matter. The nine used here are a good starting point.

Should the biggest DG set always go first?

No. Size matters, but a large standby set that runs 60 hours a year may avoid less PM than a mid-sized set that runs daily beside an air intake. The illustrative example shows a 250 kVA set ranking above four larger sets for exactly that reason.

What if two sets have the same score?

Use a tie-break rule written before scoring. A common order is regulatory score, then exposure, then run hours, then downtime availability. If the sets are a redundancy pair, they cannot be done together anyway, so the tie-break simply decides which goes first.

How often should we re-rank?

At the end of every phase, and whenever a trigger occurs, such as a new notification, a big change in run hours, a set failure or a budget change. Re-ranking takes minutes once the spreadsheet exists.

Plan Your Phased Rollout With Aceget

Aceget supplies CPCB type-approved Retrofit Emission Control Devices for DG sets from 25 kVA to 2500 kVA. You can review our certifications, and if you are planning a multi-set or multi-site programme, contact our team with your set list, ratings and run hours to discuss sequencing and survey needs.

Related Reading



3 Comments

Leave a Reply