- October 29, 2026
- Posted by: editor
- Category: RECD & Emission Control Devices
The neighbouring tower went up fast. Within a year its fourth-floor windows sat level with the DG chimney of the commercial building next door, and complaints followed. The facility team raised the stack by 6 metres. The fabricator welded on the extension and left. Nobody touched the RECD as-built drawings.
Two years later, the testing team arrived to find the sampling port well above the old platform, with no safe way to reach it. Back-pressure at the engine outlet was above the engine maker’s limit. The extension had added length and a bend, the RECD was still cleaned on the old schedule, and the drawing on file showed the original stack. Nobody could say when the problem began, because the change itself was never recorded.
This post sets out a change-control workflow for any exhaust modification on a DG set fitted with an RECD: Trigger, Capture, Revise, Verify, Distribute and Archive. If you are still preparing the original drawing, start with our guide on what an RECD general arrangement drawing should include; everything below assumes that drawing exists and the site has moved away from it.
Why RECD as-built drawings drift away from the site
Drawings rarely become wrong in one dramatic step. They drift: a support moved to clear a cable tray, a silencer swapped for whatever was in stock, a bellows added after a cracked flange. The result is a set of RECD as-built drawings that describe a system which no longer exists. That matters for three practical reasons:
- Engineering: back-pressure, thermal growth and support loads depend on actual pipe length, diameter and bends.
- Compliance: inspectors, laboratories and your State Pollution Control Board (SPCB) may rely on documents in your consent file. A mismatch costs credibility before any reading is taken.
- Warranty and service: suppliers base decisions on the configuration they approved.
Stage 1: Trigger — which modifications require an update?
The simplest rule: if a tape measure, a camera or a pressure gauge would now give a different answer from the drawing, the drawing needs a revision.
Adapt this table to your site and your supplier’s guidance.
| Modification | Drawings affected | Records affected | Re-test needed? |
|---|---|---|---|
| Exhaust reroute | GA plan and elevation, isometric, support layout | Asset register, back-pressure baseline | Yes — back-pressure at stated load; leak check |
| Extra bends added | Isometric, elevation | Back-pressure budget | Yes — back-pressure |
| Pipe diameter change or reducer added | Isometric, line schedule, GA | Back-pressure budget, material list | Yes — back-pressure |
| Silencer replaced or relocated | GA, isometric, equipment list | Asset register, supplier details | Yes — back-pressure; noise check if consent requires |
| Stack height change | Elevation, chimney detail, access drawing | Consent file (check conditions), access register | Yes — back-pressure; sampling access check |
| Sampling port relocated | Chimney detail, access drawing | Test procedure, consent file where referenced | Confirm port location suits test method before next test |
| RECD reoriented or relocated | GA plan and elevation, isometric, clearance drawing, foundation/support detail | Asset register, warranty file, commissioning record | Yes — back-pressure, leak check, clearance check; inform supplier first |
| Support or hanger changes | Support layout, structural detail | Inspection checklist | Visual and alignment check; thermal growth review |
| Bellows added or replaced | Isometric, GA | Spares list | Leak check; alignment check |
| Insulation or heat shield changes | Insulation detail, GA notes | Maintenance checklist | Surface temperature check |
| Sensor relocated (if your RECD has sensors) | Instrument location drawing, wiring diagram | Calibration records, controller settings | Confirm readings against previous baseline |
| Control or power cable reroute | Cable route drawing, wiring diagram | Cable schedule | Insulation and continuity checks by a qualified electrician |
Two triggers are commonly missed: a “like-for-like” replacement that is not quite like-for-like (same flange, different silencer internals), and work by another trade, such as a civil contractor moving a pipe support. Ask every contractor who works near the exhaust: “Did you change anything on the line?”
Who should raise the trigger?
Name one owner of exhaust change control, usually the facility engineer or DG in-charge, who opens a change record the moment a modification is planned or discovered and keeps it open until Stage 6 is complete. If you run a shift handover log for the RECD, add a line for “exhaust or RECD modification in progress” so night and weekend staff know the configuration is in flux.
Turbocharger, manifold and overhaul work often disturbs the exhaust connection. Our sibling guide on coordinating DG engine repairs with the RECD service team covers how to plan that work; this post picks up the drawing and record trail that should follow it.
Stage 2: Capture — measuring what is actually there
Never revise a drawing from memory or the fabricator’s quotation. Capture the installed condition after the work and before insulation hides anything; where it already does, note what was not verified.
Exhaust surfaces stay hot long after shutdown. Isolate the DG set using your lockout/tagout procedure before anyone climbs or measures near the line; the OSHA guidance on controlling hazardous energy is a useful generic reference for the principle, though your own site safety rules govern. Use proper access for any work at height.
Measurements to take
- Pipe lengths: each straight run, measured centreline to centreline between fittings. Record in millimetres.
- Bends: count every bend, note angle (90°, 45° or other) and whether it is a long-radius bend, short-radius elbow or mitred fabrication. Mitred bends usually behave differently from smooth bends, so note the number of segments.
- Diameters: nominal bore and, where possible, measured outside diameter. Note every reducer or expander and its direction.
- Elevations: height of key points above finished floor or roof level, including the stack outlet and sampling port.
- Support positions: type (fixed, guided, sliding, spring hanger), location and what it is fixed to.
- Flexible elements: location and length of each bellows or flexible connector. Our post on flexible bellows in the RECD exhaust system explains why their position matters.
- Clearances: distance from the RECD and pipe to walls, ceilings, cable trays, combustibles and access routes.
- Equipment data: nameplate of any new silencer, bellows or fitting, with make, model and serial number.
Photographs that are actually useful
Most site photos are useless six months later because nobody can tell scale, location or direction. Make each one count:
- Include a scale reference: a measuring tape held against the pipe, or a marked survey staff.
- Photograph each bend and support from a consistent direction, and note that direction (for example “looking north”).
- Take one wide shot of the whole run, then close-ups and straight-on nameplate shots.
- Name files with the date, asset and location, not “IMG_4471”.
Stage 3: Revise — drawing revision control that people can follow
Most sites cut corners here: a new PDF is saved over the old one and the history disappears. Good drawing revision control only needs to be consistent.
Revision numbering
Choose one scheme, for example:
- Letters (A, B, C) for issues before construction is complete.
- Numbers (0, 1, 2) or a suffix such as “AB” for as-built and later revisions.
Whichever convention you use, the revision block, file name and drawing register must all show the same revision. A title block saying Rev C beside a file called “final_v2” is where confusion starts.
Clouding and change notes
Cloud every changed area with a triangle carrying the revision identifier. In the revision block, describe the change in plain words: “Stack extended 6,000 mm; sampling port relocated to EL +18.500; platform added”, not just “updated as per site”.
Remove the previous revision’s clouds when issuing a new one; the history stays in the revision block.
A sample revision block (illustrative)
| Rev | Date | Description | Drawn | Checked | Approved |
|---|---|---|---|---|---|
| A | 2024-03-12 | Issued for construction | RK | SM | PV |
| B | 2024-05-20 | As-built after commissioning; support S4 moved 300 mm east | RK | SM | PV |
| C | 2026-08-14 | As-built: exhaust extended 9,000 mm with 2 additional 90° bends; new supports S7–S9; bellows B2 added | AJ | SM | PV |
Each line should make sense on its own, and every revision needs a checker and approver distinct from the drafter.
The as-built stamp
An as-built stamp should mean “verified against the installed system by a named person on a stated date”, not “the last version we had”. Include:
- The words “AS-BUILT”
- Name and signature of the person who verified the site
- Date of site verification, written as YYYY-MM-DD
- Reference to the capture sheet or survey record
Note anything not verified, for example “Pipe under insulation between points 7 and 9 from fabricator’s record”.
Superseded copies
Never delete the old revision. Move it to a superseded folder, mark every page “SUPERSEDED BY REV C” with the date, and collect printed copies from the DG room and contractors. An old print on the plant-room wall is how outdated layouts get rebuilt.
Which documents to revise alongside the GA
The as-built GA drawing for the DG exhaust is rarely the only document affected. Check the isometric, support layout, chimney elevation, access drawing, insulation detail and cable route drawing. If any control or power cable was rerouted, check the new route against the advice in routing RECD cables near hot exhaust lines.
Stage 4: Verify — the back-pressure re-check after an exhaust change
A revised drawing describes the system; verification proves it still works. This is where the opening story went wrong.
Back-pressure at a stated load
Back-pressure depends on gas flow, and so on engine load. A reading without its load means nothing. For each verification:
- Run the DG set at a defined load, ideally the same load used for the original commissioning baseline.
- Allow the engine and RECD to reach stable operating temperature.
- Measure static back-pressure at the point the engine maker specifies, typically close to the turbocharger outlet or exhaust manifold outlet.
- Record load (kW and percentage), exhaust temperature if available, ambient conditions and the instrument used.
- Compare the reading with two numbers: the engine maker’s maximum allowable back-pressure and the previous baseline at the same load.
Our explainer on how exhaust back-pressure affects a DG set covers why excess back-pressure harms fuel consumption and engine life. You need margin, not just a pass.
RECD resistance can also change over a service interval. Filter-type designs generally see it rise as soot and ash accumulate; DieselNet’s overview of ash in particulate filters explains why ash does not burn off. Ask your supplier what rise to expect and include it in your margin.
Leak and joint checks
After the first run to temperature, cool down, isolate and inspect each new flange, clamp and weld for soot tracks or gasket extrusion. A leak upstream of the RECD releases untreated exhaust; one downstream can distort sampling results.
Access and clearance checks
Can the RECD still be opened, cleaned or have its core lifted out? Our guide on service clearance around an RECD lists the typical clearances to confirm.
If the stack was raised or rerouted, confirm the sampling port is still safely reachable and suitably positioned for the test method. Our posts on safe access to RECD sampling ports on tall chimneys and on how exhaust sampling location affects RECD test results set out what to look for.
Thermal movement and supports
A longer pipe expands more; revisit how growth is absorbed using planning for thermal expansion at RECD exhaust connections. Mark new supports as fixed, guided or sliding so nobody later locks a sliding one.
Stage 5: Distribute — who needs the new revision?
A drawing on one engineer’s laptop has not been issued. Record who received which revision, and when.
| Recipient | Why they need it | What to send |
|---|---|---|
| O&M or AMC contractor | They work on the system and must not rebuild an old layout | Revised drawings, verification results, updated checklists |
| RECD supplier | Warranty, service planning and spares depend on the approved configuration | Change summary, revised GA and isometric, back-pressure results |
| EHS lead | Access, hot-surface and work-at-height risks may have changed | Access drawing, clearance check, revised risk notes |
| Consent or compliance file | Inspectors may compare documents with the site | Revised drawings where consent documents reference the layout |
| Insurer (where the policy requires notification) | Material changes to plant can affect cover | Change summary; check policy wording |
| Testing laboratory (before next test) | Port location and access affect test planning | Chimney elevation and access drawing |
Telling the RECD supplier
Notify the supplier in writing before modifying the RECD or the pipework around it, and promptly after any change affecting back-pressure. Our guide to RECD warranty terms, parts, labour and exclusions explains the kinds of conditions to look for in your own certificate. For an older model, also confirm spares availability, as discussed in planning parts and support when an RECD model is discontinued.
Regulatory notification
Some consent conditions require the SPCB to be informed of changes to stacks or pollution control equipment; others do not. Read your consent document and, if unclear, ask your SPCB regional office or environmental consultant. Background on CPCB’s role and published guidance is available on the Central Pollution Control Board website, and our page on DG set emission regulations gives a broader overview. Never treat a modification as a reason to run the DG without the RECD while paperwork catches up; operating without the approved device is a compliance risk in its own right.
Stage 6: Archive — naming, dating and the master register
Archiving makes the next modification easier. Someone will need to know what changed, when and why.
File naming conventions
A predictable pattern beats a clever one:
SITE-DG2-EXH-GA-001_RevC_AB_2026-08-14.pdf
That name carries site, asset, system, drawing type, sequence number, revision, status (AB for as-built) and date. Write dates in the year-month-day order defined by ISO 8601, so files sort correctly and nobody confuses 08/09 with 09/08.
A sample drawing register (illustrative)
| Drawing no. | Title | Current rev | Status | Date | Location of master | Superseded revs |
|---|---|---|---|---|---|---|
| SITE-DG2-EXH-GA-001 | DG2 exhaust and RECD general arrangement | C | As-built | 2026-08-14 | Engineering drive / Drawings / DG2 | A, B |
| SITE-DG2-EXH-ISO-002 | DG2 exhaust isometric | C | As-built | 2026-08-14 | Engineering drive / Drawings / DG2 | A, B |
| SITE-DG2-EXH-SUP-003 | DG2 exhaust support layout | B | As-built | 2026-08-14 | Engineering drive / Drawings / DG2 | A |
| SITE-DG2-EXH-CHM-004 | DG2 chimney elevation and sampling port | A | As-built | 2024-05-20 | Engineering drive / Drawings / DG2 | — |
Not every drawing changes each cycle. Add a remarks column to record “checked 2026-08-14, no change” so an old revision is not mistaken for an oversight.
Keep the evidence with the drawing
Store the capture sheet, photos, readings and distribution record with the revised drawing. A drawing without its evidence is just a picture.
Records beyond the drawings
- Asset register: new silencer, bellows or supports should appear with make, model, serial number and installation date. Removed items should be marked as removed, not deleted.
- Baselines: the back-pressure baseline at stated load, and any sensor baselines if your RECD has a controller or differential pressure measurement, must be replaced by the post-modification values. Keep the old values for comparison.
- Consent and compliance file: update where your consent conditions reference the layout or require notification. Check with your SPCB if in doubt.
- Warranty file: keep a copy of the written notice to the RECD supplier and their reply.
These records also protect future owners. If the building or plant is sold, a buyer’s engineer will ask for this history; our sibling post on due diligence when buying a building with an existing RECD lists the questions they are likely to ask. And when the device eventually reaches end of life, accurate drawings make removal planning much simpler, as covered in how to plan RECD decommissioning and removal.
Worked example: a 9 m extension with two extra bends (illustrative)
All values below are illustrative. Real figures depend on pipe size, bend geometry, gas flow and temperature, and must come from your engine maker, RECD supplier and site measurements.
The situation
A 500 kVA DG set at a commercial site, fitted with an RECD sized for its rating (see our RECD for 500 kVA DG sets page for the product range). A new boundary wall forces the exhaust to be extended by 9 metres, with two additional 90° bends to clear the wall. Pipe diameter is unchanged.
Step 1: The original back-pressure budget
All values in kPa, at 75% load, illustrative.
| Item | Estimated back-pressure (kPa) |
|---|---|
| RECD (clean, after service) | 3.5 |
| Silencer | 2.0 |
| Original pipework (straight runs plus 4 bends) | 1.3 |
| Total estimated | 6.8 |
Engine maker’s maximum allowable back-pressure (illustrative): 10.0 kPa.
Measured at commissioning (Rev B baseline), 75% load: 6.9 kPa. That is close to the estimate, which gives confidence in the budget.
Step 2: Estimating the added resistance
Using illustrative unit values supplied by the designer:
- Straight pipe: 0.05 kPa per metre × 9 m = 0.45 kPa
- 90° bends: 0.25 kPa each × 2 = 0.50 kPa
- Added resistance: 0.45 + 0.50 = 0.95 kPa
New estimated total with a clean RECD: 6.8 + 0.95 = 7.75 kPa.
Step 3: Adding the service-interval allowance
The supplier advises (illustrative) that RECD resistance may rise by up to 2.0 kPa between scheduled cleanings at this duty.
Estimated end-of-interval total: 7.75 + 2.0 = 9.75 kPa.
Margin to the limit: 10.0 − 9.75 = 0.25 kPa, which is 0.25 ÷ 10.0 = 2.5% of the limit.
Step 4: Measuring after the modification
After the extension, with a freshly cleaned RECD, the set is run at the same 75% load and allowed to stabilise.
- Measured back-pressure: 7.9 kPa
- Increase over the Rev B baseline: 7.9 − 6.9 = 1.0 kPa
- Projected end-of-interval value: 7.9 + 2.0 = 9.9 kPa
- Projected margin: 10.0 − 9.9 = 0.1 kPa, or 1% of the limit
Step 5: The decision
The system passes on the day, but a 1% margin is too thin. The team decides to upsize the new pipe section at the next planned shutdown and, meanwhile, sets an internal action level of 9.0 kPa at 75% load to trigger RECD cleaning. Both decisions are recorded, and the drawing will be revised again after the upsizing.
Step 6: Revision history entries
| Date | Record | Entry |
|---|---|---|
| 2026-07-28 | Change record CR-DG2-2026-03 opened | Exhaust extension 9 m with 2 × 90° bends planned; supplier notified in writing |
| 2026-08-09 | Capture sheet | Site survey after fabrication; 42 photos; insulation not yet fitted |
| 2026-08-12 | Verification record | Back-pressure 7.9 kPa at 75% load (baseline 6.9 kPa); leak check passed; clearance check passed |
| 2026-08-14 | Drawings GA-001, ISO-002, SUP-003 | Issued at Rev C as-built; Rev B marked superseded |
| 2026-08-16 | Distribution record | Issued to AMC contractor, RECD supplier, EHS lead and compliance file |
| 2026-08-16 | Asset register and baselines | New supports and bellows added; back-pressure baseline updated; action level 9.0 kPa set |
Common failure points
Gaps that show up most often when exhaust modification documentation is reviewed:
- No trigger. Another trade did “minor work” and the drawing owner never heard.
- Drawing revised from the quotation, not the site. The fabricator added an unplanned bend.
- Back-pressure recorded without load. The number cannot be compared with anything.
- Baseline overwritten. The size of the change is lost.
- Old prints left in circulation. A later repair rebuilds the previous layout.
- Supplier not told. A warranty question becomes an argument about configuration.
- Sampling port forgotten until a test is booked.
- Supports not classified. A sliding support is locked and a flange cracks.
- Change record never closed once the DG is back in service.
A closing checklist on each change record, signed stage by stage, removes most of these.
FAQ
Do I need to update RECD as-built drawings for a minor exhaust change?
Yes, if a measurement or photograph would now differ from the drawing: a pipe length, bend, support position or component. Small changes accumulate.
Is back-pressure re-testing needed after every exhaust modification?
Re-test whenever the change affects the gas path: rerouting, extra bends, a diameter change, a silencer replacement, a stack height change or RECD relocation. Measure at a stated load and compare with both the engine maker’s limit and the previous baseline.
Who should approve a revised as-built drawing?
Someone other than the drafter should check it against the site survey, and a responsible engineer should approve it, with the verifier and date on the as-built stamp.
Should I inform the SPCB after modifying the DG exhaust?
It depends on your consent conditions. Some require notification of changes to stacks or pollution control equipment. Read your consent document and confirm with your SPCB regional office or environmental consultant if the wording is unclear.
What should I do with superseded drawings?
Keep them in a separate superseded folder, marked with the replacing revision and date. Collect and mark or destroy printed copies on site so nobody works from an outdated layout.
Does modifying the exhaust affect my RECD warranty?
It can, depending on your warranty terms and whether the change moves the installation outside the conditions the supplier approved. Notify the supplier in writing, share the revised drawings and back-pressure results, and keep their reply on file.
Planning an exhaust change around your RECD?
If you are about to reroute, extend or rebuild an exhaust that carries an RECD, it helps to talk to the device supplier before the fabricator starts cutting. Aceget supplies CPCB type-approved retrofit emission control devices for DG sets from 25 kVA to 2500 kVA, and you can review our type-approval certifications online. Share your current drawings, the proposed change and your latest back-pressure readings through our contact page, and our team can advise on the questions to settle before the work begins.
Related Reading
- What an RECD General Arrangement Drawing Should Include
- How Exhaust Back-Pressure Affects a DG Set
- How to Coordinate DG Engine Repairs with the RECD Service Team
- Buying a Building with an Existing RECD: Due Diligence Questions
- How to Plan RECD Decommissioning and Removal
- Safe Access to RECD Sampling Ports on Tall Chimneys
[…] entry should give date, who, what and values before and after. See updating RECD drawings and records after exhaust modifications and RECD firmware update questions before a service […]