Most sites treat the end of an emission control device as a single line on a work order: “remove RECD, send to scrap.” In practice, RECD decommissioning touches lifting and rigging, possibly hot work, electrical isolation, several different waste streams, a pollution consent file and an asset register. Skip the planning and you end up with a crane booked for the wrong day, a controller dumped with general scrap, or an auditor two years later asking where a certified device went.
This guide treats removal as what it really is: a small project with a scope, phases, owners and a closing report. It starts with the one question that changes everything downstream, namely why the device is coming out, and then walks through six phases from approvals to records close-out. An illustrative cost example and a list of common mistakes follow, so you can build your own plan and budget before the first bolt is loosened.
One principle runs through the whole article. If a DG set stays in service, it must stay compliant. Removing an RECD to keep an engine running is not decommissioning; it is a compliance risk, and the planning below assumes you never do it.
Why RECD decommissioning is a project, not a scrap job
An RECD on a mid-size or large DG set is a heavy, hot-service pressure part of the exhaust system, often mounted at height, in a basement, or on a rooftop. It may carry sensors, a controller and heater supplies wired into the DG panel. Its filter or catalyst element has trapped soot and ash for years. Its certificate and installation records sit in your consent file.
That gives four workstreams, usually with four different owners: mechanical and lifting, electrical and controls, waste and materials, and compliance records. Good RECD decommissioning coordinates all four in one plan.
Why are you removing it? The decision fork
Before any method statement, decide the destination. The reason for removal largely decides whether the device is reused, stored, returned, refurbished or scrapped, and that in turn decides how carefully it has to be handled.
| Reason for removal | Usual destination | What it changes in the plan |
|---|---|---|
| 1. DG set retired, no replacement | Scrap, or sale/return if device is young | Waste segregation and disposal receipts dominate |
| 2. DG replaced with a new CPCB IV+ genset | Scrap, store, or transfer to another set | Timing must match the new set’s commissioning |
| 3. Switch to dual fuel or gas | Depends on whether the converted set still needs the RECD | Confirm compliance route before removal |
| 4. Relocation or transfer | Reuse on same or another set | Careful handling, packing, transport, re-verification |
| 5. Failed device replaced | Return to supplier, refurbish or scrap | Warranty evidence and supplier coordination |
Fork 1: the DG set is being retired altogether
If the site has moved to reliable grid supply, a solar-plus-storage system, or simply no longer needs backup, the generator and its RECD leave together. The whole-generator side, including engine fluids and the alternator, is covered in our guide on how to safely dispose of an old diesel generator. The RECD should be its own sub-package, because its element, insulation and electronics should not ride along with the engine block to a general scrap yard. If the device is young, check supplier buy-back or reuse elsewhere in your group first.
Fork 2: the DG set is replaced by a new CPCB IV+ genset
Many owners weigh up retrofitting an old set against buying a new one, and the trade-offs are laid out in our RECD versus new CPCB IV+ genset cost comparison. Once the decision is made, the old set and its RECD come out together. If the old set must remain available until the new one is commissioned, its RECD stays on until then; never strip it and keep the set “just in case”.
Fork 3: switching to dual fuel or gas
Converting to dual fuel with a dual-fuel kit, or moving to a gas genset, changes the emission profile, but it does not automatically mean the RECD can come off. The compliance route for a converted engine depends on your state’s rules and your consent conditions. Our comparison of RECD and dual-fuel kit options explains why some sites use both. Confirm with your SPCB and your consent document before scheduling any removal on a set that will keep running.
Fork 4: relocation or transfer
When a DG set moves, or an RECD goes to a different engine, the device is a reusable asset. Whether a transfer is sensible is answered in our post on whether an RECD can be transferred to another diesel generator. For removal, it means gentler rigging, capped openings, labelled cables and proper packing.
Fork 5: a failed device is being replaced
If the element is cracked or the housing corroded through, coordinate with the supplier first: they may want the failed unit returned for inspection, especially under warranty. If the model is no longer made, read our guide on planning for parts and support when an RECD model is discontinued before deciding between a like-for-like replacement and a fresh selection.
The phase plan at a glance
The table below is a Gantt-style summary of a typical removal. Durations are illustrative for a single mid-size RECD on an accessible site; basements, rooftops, multi-set plant rooms and approval delays all stretch them.
| Phase | Key tasks | Owner | Typical duration (illustrative) | Wk 1 | Wk 2 | Wk 3 | Wk 4 | Wk 5 | Wk 6 |
|---|---|---|---|---|---|---|---|---|---|
| 1. Planning and approvals | Decide destination, check consent conditions, supplier buy-back, budget | Facility manager / EHS | 1–2 weeks | X | X | ||||
| 2. Survey and method statement | Weights, lift route, rigging plan, hot work need, risk assessment | Rigging contractor / site engineer | 3–5 days | X | |||||
| 3. Isolation and preparation | LOTO, cool-down, electrical isolation, sensor disconnection, drain condensate | Electrician / DG operator | 1 day | X | |||||
| 4. Removal | Unbolt, support exhaust, lift out, blank or reconnect exhaust | Rigging and exhaust contractor | 1–2 days | X | |||||
| 5. Destination handling | Pack for reuse, or segregate waste streams and dispatch | Stores / EHS / recyclers | 1–3 weeks | X | X | X | |||
| 6. Records close-out | Retire asset, update consent file and drawings, archive receipts | Facility manager / compliance | 1 week | X | X |
Planning takes longer than the physical removal, and destination handling often runs for weeks because recyclers collect on their own schedules. Do not close the project until Phase 6 is signed.
Phase 1: Planning approvals for RECD decommissioning
Protect the compliance of whatever keeps running
The first planning question is about the DG sets that will still operate. A set that requires an RECD under your consent or applicable directions should never run without it, not even “only for testing”. In Delhi NCR, CAQM directions on DG use, including GRAP-stage restrictions, make a non-compliant run during a pollution episode a serious exposure.
Check your consent conditions
Consent to Operate documents often list DG sets by rating and sometimes by the emission control arrangement. Removing a set, adding a new one, or changing control equipment may require you to inform the SPCB or apply for an amendment. The requirement varies by state and by consent, so read the document and, where in doubt, ask the board or your environmental consultant. Keep a copy of any intimation letter for Phase 6.
Talk to the supplier early
Ask the RECD supplier about buy-back, take-back or refurbishment; whether they want a failed unit returned; lifting weights and the original GA drawing; handling notes for the element and insulation; and whether their engineer can attend the disconnection.
Method statement and risk assessment
Even a small removal deserves a written method statement and risk assessment listing the sequence, people, equipment, permits (height, hot work, isolation, lifting), exclusion zone and emergency arrangements.
Phase 2: Survey and method statement
Know the weight and the lift points
Get the RECD’s weight from the nameplate, the GA drawing or the supplier, and add an allowance for accumulated soot, ash and any insulation cladding. Identify the designed lifting lugs. Never assume that a flange, a sensor boss or an insulation support bracket can take a lifting load.
Walk the removal route
The installation route may no longer exist; cable trays, fire doors or panels may have been added since. Walk the route to the loading point and note every pinch point, floor loading limit and turn.
- Basement DG rooms often need the device lowered to the floor, moved on skates or a pallet truck, and lifted out through a hatch or ramp. Our basement DG room space and access planning guide covers the same constraints in reverse.
- Rooftop installations usually need a mobile crane or a temporary hoist, a structural check of the support frame during the unloading sequence, and a wind limit for the lift. The issues are set out in our article on rooftop RECD support, lifting and access.
Choose the lifting method
Match the equipment to weight, height and headroom: mobile crane, hydra or chain blocks on a certified beam. Include any scaffolding in the schedule, and file the rigger’s and tackle’s test certificates.
Decide whether hot work is needed
Old exhausts often have seized bolts or welded spools. If cutting is unavoidable, plan a hot work permit, remove combustibles and keep a fire watch after cutting stops, because soot-laden parts can smoulder. Never cut a device intended for reuse.
Phase 3: Isolation and preparation
Lockout and tagout
Isolate the DG set so it cannot start, whether manually, through an AMF panel or remotely. Apply locks and tags at the starting system, the battery, the fuel supply where appropriate, and any remote start signals. The principles of controlling hazardous energy, summarised by OSHA’s lockout/tagout guidance, are a useful reference even on Indian sites using their own permit systems. Every person working on the job should apply a personal lock.
Let it cool properly
A filter body with high thermal mass can hold heat for hours. Set a minimum cool-down period and check surface temperatures before anyone touches insulation or bolts.
Electrical isolation of controller and heaters
If your RECD has a controller, heater circuit or sensor power supply, isolate it at its source, prove it dead, and then disconnect. Do not just cut cables at the device and leave live ends in a junction box. Terminate or remove the feeder, update the panel schedule, and remove any alarm or interlock signals that the DG panel or BMS expects from the RECD, so the remaining system does not show permanent faults.
Disconnect and label sensors
Where the design uses sensors, disconnect and label both ends. For reuse, cap ports and connectors; for scrap, still remove sensors, because they belong in the electronics stream.
Drain condensate and clean loose deposits
If there is a condensate drain or trap, drain it into a container and handle the liquid as you would other oily or contaminated water on site. Brush or vacuum loose soot from accessible surfaces into a sealed bag, rather than letting it fall during the lift. How to handle and document these residues is covered in our sibling guide on handling soot and ash removed during RECD servicing.
Phase 4: Removal
Support the exhaust before releasing flanges
The RECD often carries part of the exhaust load. Before any bolts come out, support the upstream and downstream pipework with temporary hangers or props so nothing drops or swings when the device is released. Check the condition of bellows and supports; old bellows can crack once disturbed.
Unbolt in a controlled sequence
Take the rigging load first, then release flanges, then mounting bolts. For reuse, bag and label gaskets and fasteners to identify the connection type.
Deal with the open exhaust
What happens to the exhaust opening depends on the fork you are on:
- DG retired or replaced: the old exhaust is usually stripped back with the set. Blank any openings in shared stacks or building penetrations so rain and birds cannot enter.
- DG staying, new RECD arriving: fit a temporary blank and keep the DG locked out until the new device is installed and commissioned. A temporary straight spool to let the set run in the meantime is exactly the kind of bypass that creates a compliance problem; do not do it.
- DG converted or relocated: follow the engineered design for the new arrangement, with the set out of service until it is complete.
Protect neighbouring services
Protect cable trays, fuel lines and fire detection heads from swinging loads. In shared rooms, confirm only the intended set is isolated.
Phase 5: Destination handling
Once the device is on the floor, the project splits according to the destination decided in Phase 1.
Reuse or storage
If the RECD is going to another set, or into storage pending a decision, treat it as new stock. Cap every opening, keep the element dry, protect sensors and connectors, and store it indoors on a pallet. The same practices described in our guide to storing an RECD before installation apply to a used unit, with one addition: record its operating hours and last service condition on the storage tag.
For moving it, use proper crating, bracing and lifting points rather than a loose truck load. Our article on how to package and transport an RECD without damage has the details. Before it is fitted to anything else, plan a re-verification with the supplier.
Refurbishment
Sometimes the housing is sound but the element is tired. A cleaned or refurbished core may be worth considering, but only with clear acceptance criteria and supplier involvement. The considerations are covered in our post on refurbished RECD filter core reuse. Keep the refurbishment report with the device’s records.
Scrap: segregate before you sell
Sending the whole assembly to a scrap dealer is the easiest option and usually the wrong one. An RECD is several materials in one shell, and each needs its own route.
| Stream | Typical content | Suggested route |
|---|---|---|
| Housing and frame | Mild steel or stainless steel, flanges, fasteners | Metal recycler; separate stainless from mild steel for better value |
| Filter or catalyst element | Ceramic substrate, metal substrate, possible catalyst coating | Ask the supplier and a specialist recycler; coated elements may contain precious or base metals |
| Insulation and mats | Mineral wool, ceramic fibre blankets, mounting mats | Handle per site EHS procedure; some fibres need dust control and PPE |
| Soot and ash residues | Carbonaceous soot, lube-oil derived ash | Bag, label and route per SPCB guidance via an authorised handler |
| Electronics | Controller, sensors, display, power supplies | Authorised e-waste recycler |
| Cables and accessories | Copper cables, glands, trays | Cable recycler or general metal recycler |
A few notes on the trickier streams:
- Elements and catalysts. Depending on the design, the element may be a ceramic wall-flow filter, a metallic substrate or a coated flow-through core. If it carries a catalytic coating, it may have recoverable metal value. Do not guess; ask the supplier what it contains and get a quote from a recycler who handles such material.
- Insulation. Old high-temperature insulation can shed fibres when disturbed. Wet it lightly or bag it in place, wear appropriate respiratory protection, and follow your EHS team’s procedure. If you are unsure what the material is, ask the supplier or have it identified before handling.
- Soot and ash. Ash in particulate filters is mostly incombustible material from lube-oil additives, as explained in DieselNet’s overview of filter ash. How such residues are classified locally is not something to assume; follow our sibling soot and ash post and confirm with your SPCB and an authorised handler.
- Electronics. India has E-Waste (Management) Rules, and the Hazardous and Other Wastes Rules cover other categories; both are published by the Ministry of Environment, Forest and Climate Change. Confirm with your recycler how controllers and sensors should be documented under the current rules.
For the wider regulatory picture on generator scrap, see our guide to generator scrap disposal rules in India.
Get receipts for every stream
For each stream, get a dated receipt naming material, quantity and recipient, and photograph segregated piles before collection.
Phase 6: Records close-out
Retire the asset, do not delete it
Mark the RECD “decommissioned” in your asset register with date, reason and destination, keeping its serial number, certificate and service history. Deleting it raises more questions than it answers.
Update the consent file
Add the removal date, any SPCB intimation or amendment, and a note of the replacement arrangement (new genset, new RECD, conversion, or no DG). The Central Pollution Control Board sets the type approval framework for RECDs, but your consent file is where an inspector will look for site-level history, so make sure it tells a complete story.
Update drawings and schedules
Exhaust layouts, single-line diagrams, panel schedules and BMS point lists all change when an RECD comes out. Our sibling guide on updating RECD drawings and records after exhaust modifications explains which documents to revise and how to mark superseded versions.
Archive the evidence pack
A complete close-out pack contains:
- The planning note with the decision fork outcome.
- Method statement, risk assessment and permits.
- Lifting equipment and rigger certificates.
- Before, during and after photographs.
- Electrical isolation and disconnection record.
- Disposal receipts for each waste stream, or the transfer or return document.
- SPCB correspondence, if any.
- Updated asset register extract and revised drawings.
- The original type approval certificate and installation records, marked “decommissioned on [date]”.
When a property changes hands, the buyer’s team will ask about emission control history, as covered in our sibling post on buying a building with an existing RECD. A tidy file answers them in minutes.
Illustrative cost and value example: removing an RECD from a 1010 kVA DG set
The figures below are illustrative only; actual rates vary by city, access and scrap prices on the day. The scenario: a factory is retiring an old 1010 kVA DG set and scrapping its RECD. The device sits on a ground-level frame inside a DG room with a roller shutter, and no hot work is needed.
Costs
| Item | Basis (illustrative) | Amount |
|---|---|---|
| Mobile crane | 1 day at ₹18,000 | ₹18,000 |
| Rigging crew | 4 people × 2 days × ₹1,200 | ₹9,600 |
| Electrician for isolation and disconnection | Lump sum | ₹3,000 |
| Exhaust contractor for supports and blanking | Lump sum | ₹12,000 |
| Transport to recycler yard | One truck trip | ₹8,000 |
| Insulation bagging and disposal | Lump sum | ₹4,000 |
| E-waste handling and documentation | Lump sum | ₹1,500 |
| Total cost | ₹56,100 |
Check: ₹18,000 + ₹9,600 + ₹3,000 + ₹12,000 + ₹8,000 + ₹4,000 + ₹1,500 = ₹56,100.
Recoverable value
Assume the housing and frame yield 750 kg of mild steel scrap at an illustrative ₹28 per kg.
750 × ₹28 = ₹21,000.
Net position
₹56,100 − ₹21,000 = ₹35,100 net cost.
The element has not been counted. If the supplier confirms a catalytic coating and a recycler quotes for it, that may reduce the net cost; if the element needs special handling, it may increase it. Either way, getting that quote before the crane day is part of Phase 1, not an afterthought. If the device were young enough to transfer or sell back, the economics would change entirely, which is why the decision fork comes first.
Common RECD decommissioning mistakes
- Removing the RECD while the DG set is still expected to run. Any gap where a set that needs an RECD operates without one is a compliance breach, whatever the reason.
- Booking the crane before the survey. Wrong capacity, wrong reach, or no hardstanding means a wasted day and a second hire charge.
- Lifting by the wrong points. Flanges and brackets are not lifting lugs.
- Cutting cables instead of isolating circuits. Live ends left in a junction box are a hazard for the next person in the room.
- Leaving permanent alarms on the DG panel or BMS. Unremoved RECD signals become nuisance faults that operators learn to ignore.
- Scrapping the whole assembly as one lot. You lose value on the steel and element, and lose control of where the insulation, residues and electronics end up.
- No receipts. Without disposal paperwork, you cannot prove where the device and its materials went.
- Deleting the asset record. Retire it instead and keep its history.
FAQ
Can I remove the RECD and keep running the DG set until the new device arrives?
No. If your DG set needs an RECD under its consent or applicable directions, running it without one is a compliance risk that can lead to sealing and penalties. Keep the set locked out until the replacement is installed and commissioned, or arrange compliant temporary power.
Do I need to inform the pollution control board when I decommission an RECD?
It depends on your consent conditions and your state board. Some consents list DG sets and their control equipment, so changes may need intimation or an amendment. Read your consent document and confirm with the SPCB or your environmental consultant.
Can an old RECD be reused on another generator?
Sometimes, if it suits the other engine and the supplier agrees. Plan re-verification before reuse.
What is the old filter element worth?
That depends on its construction. Coated elements may contain recoverable metals, while plain ceramic elements may have little value. Ask the supplier what the element contains and get a quote from a specialist recycler.
How long does RECD removal take?
The physical removal of a single device often takes one to two days, but planning, approvals, waste dispatch and records can stretch the full project to four to six weeks. Basements, rooftops and multi-set rooms take longer.
Who should own the decommissioning project?
Usually the facility manager or plant engineer, with EHS owning waste handling and permits, an electrician owning isolation, and a competent rigging contractor owning the lift. Name one person to sign off Phase 6.
Replacing, Relocating or Retiring an RECD? Plan It with Aceget
Whether you are swapping a failed device, moving to a new genset, or retiring a DG set, Aceget can help you think through the next step, from selecting a replacement retrofit emission control device for a set that stays in service to sharing the certifications your consent file needs. Share your DG rating, site layout and the reason for removal, and contact the Aceget team to discuss options before the crane is booked.
Related Reading
- Handling Soot and Ash Removed During RECD Servicing
- Updating RECD Drawings and Records After Exhaust Modifications
- When an RECD Model Is Discontinued: Planning for Parts and Support
- Buying a Building with an Existing RECD: Due Diligence Questions
- Can an RECD Be Transferred to Another Diesel Generator?
[…] lies. If the device or the element is ever sold, moved or handed over, the file goes with it; see planning RECD decommissioning and removal for the end-of-life side of record […]